Zenobe New Deer Battery Storage
- Connection date
- 31 Oct 2029
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 200 MW
- Connected now
- 0 MW
- Still to connect
- 200 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-001778
- In the register since
- March 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 30 Mar 2022 registerAdded to the register
Also at New Deer 400kV Substation
Substation view2 other projects, 760 MW still to connect at this substation in total. 300 MW is due to connect here before this project’s connection date of 31 Oct 2029.