Green Volt Offshore Windfarm
Green Volt Offshore Windfarm Ltd at New Deer 400kV Substation
- Connection date
- 31 Mar 2029
- Gate
- Not stated
- Status
- Scoping
- Planning consent
- Granted 19 Apr 2024
Marine Scotland · Source: REPD - Contract for Difference
- Allocation Round 6
- Technology
- Demand + Offshore wind
- Total capacity
- 560 MW
- Connected now
- 0 MW
- Still to connect
- 560 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-001469
- In the register since
- August 2021
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 0 | 300 | 300 | 31 Mar 2029 | Not stated | Scoping |
| 2 | 0 | 260 | 560 | 31 Oct 2033 | Not stated | Scoping |
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Aug 2025 registerCustomer changed from FLOTATION ENERGY LIMITED to Green Volt Offshore Windfarm Ltd
- 29 Aug 2025 registerStage 1: Capacity changed from 0 MW to 300 MW
- 29 Aug 2025 registerStage 1: Connection date moved from 1 Apr 2028 to 31 Mar 2029 (+12 months)
- 29 Aug 2025 registerStage 2: Capacity changed from 300 MW to 260 MW
- 29 Aug 2025 registerStage 2: Connection date moved from 31 Mar 2029 to 31 Oct 2033 (+55 months)
- 29 Aug 2025 registerStage removed (0 MW from 31 Oct 2029)
- 29 Aug 2025 registerStage removed (260 MW from 31 Oct 2033)
- 29 Jul 2025 registerNew stage added (0 MW from 1 Apr 2028)
- 29 Jul 2025 registerNew stage added (0 MW from 31 Oct 2029)
- 28 Feb 2025 registerNew stage added (260 MW from 31 Oct 2033)
- 29 Oct 2024 registerCustomer changed from FLOTATION ENERGY PLC to FLOTATION ENERGY LIMITED
- 28 Jun 2024 registerConnection point changed from Green Volt 220/66kV Offshore Substation to New Deer 400kV Substation
- 28 Jun 2024 registerTechnology changed from Offshore wind to Demand, Offshore wind
- 26 Apr 2024 registerConnection point changed from New Deer 400kV Substation to Green Volt 220/66kV Offshore Substation
- 26 Apr 2024 registerConnection date moved from 31 Oct 2029 to 31 Mar 2029 (−7 months)
- 29 Dec 2023 registerRenamed from Whirlwind Offshore Wind Farm
- 31 Jan 2023 registerCustomer changed from FLOTATION ENERGY LIMITED to FLOTATION ENERGY PLC
- 23 Dec 2022 registerCustomer changed from FLOTATION ENERGY PLC to FLOTATION ENERGY LIMITED
- 31 Aug 2021 registerAdded to the register
Also at New Deer 400kV Substation
Substation view2 other projects, 760 MW still to connect at this substation in total.