Ironbridge 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Ironbridge Green Energy Centre | IRONBRIDGE GREEN NG LIMITED | Storage with solar or wind | 400 | 30 Oct 2029 | Gate 1 | Awaiting Consents |
| Ironbridge | IGP SOLAR 16 LIMITED | Storage with solar or wind | 600 | 30 Apr 2031 | Not stated | Scoping |
| ELMYA REDNAL | ELMYA RPC UK REDNAL LIMITED | Storage | 300 | 30 Oct 2034 | Gate 1 | Awaiting Consents |
Left the register since January 2021: Ironbridge - New Connection (120 MW).
Recent changes
- Ironbridge Green Energy CentreEngland and Wales, Storage with solar or windConnection date moved from 30 Oct 2032 to 30 Oct 2029 (−36 months)−36 mo
- Ironbridge Green Energy CentreEngland and Wales, Storage with solar or windConnection date moved from 30 Oct 2029 to 30 Oct 2032 (+36 months)+36 mo
- ELMYA REDNALEngland and Wales, StorageMarked as Gate 1
- Ironbridge Green Energy CentreEngland and Wales, Storage with solar or windMarked as Gate 1
- IronbridgeEngland and Wales, Storage with solar or windStage removed (0 MW from 30 Oct 2032)
- IronbridgeEngland and Wales, Storage with solar or windRestructured from 1 stage (600 MW from 30 Oct 2032) to 2 stages (600 MW from 30 Apr 2031, 0 MW from 30 Oct 2032). First connection date −18 months−18 mo
- Ironbridge Green Energy CentreEngland and Wales, Storage with solar or windCustomer changed from INNOVA RENEWABLES LIMITED to IRONBRIDGE GREEN NG LIMITED
- IronbridgeEngland and Wales, Storage with solar or windConnection date moved from 30 Oct 2029 to 30 Oct 2032 (+36 months)+36 mo
- Ironbridge - New ConnectionEngland and Wales, Storage with solar or windLeft the register (49.9 MW from 30 Jun 2025, 49.9 MW from 30 Jun 2026, 20.2 MW from 30 Dec 2026)120 MW
- ELMYA REDNALEngland and Wales, StorageCustomer changed from ELMYA ENERGY UK 9 LIMITED to ELMYA RPC UK REDNAL LIMITED
- IronbridgeEngland and Wales, Storage with solar or windSubstation name updated in the register (from Ironbridge GSP to Ironbridge 400kV Substation)
- Ironbridge Green Energy CentreEngland and Wales, Storage with solar or windSubstation name updated in the register (from Ironbridge GSP to Ironbridge 400kV Substation)
- ELMYA REDNALEngland and Wales, StorageCustomer changed from Alcemi Storage Developments 7 Ltd to ELMYA ENERGY UK 9 LIMITED
- ELMYA REDNALEngland and Wales, StorageAdded to the registerNew
- IronbridgeEngland and Wales, Storage with solar or windSubstation name updated in the register (from Ironbridge 400kV to Ironbridge GSP)
- Ironbridge Green Energy CentreEngland and Wales, Storage with solar or windSubstation name updated in the register (from Ironbridge 400kV to Ironbridge GSP)
- Ironbridge - New ConnectionEngland and Wales, Storage with solar or windSubstation name updated in the register (from Ironbridge 400kV to Ironbridge 400kV Substation)
- IronbridgeEngland and Wales, Storage with solar or windSubstation name updated in the register (from Ironbridge to Ironbridge 400kV)
- Ironbridge Green Energy CentreEngland and Wales, Storage with solar or windSubstation name updated in the register (from Ironbridge to Ironbridge 400kV)
- Ironbridge - New ConnectionEngland and Wales, Storage with solar or windStage 3: Connection date moved from 30 Jun 2027 to 30 Dec 2026 (−6 months)−6 mo
- Ironbridge Green Energy CentreEngland and Wales, Storage with solar or windConnection date moved from 30 Oct 2028 to 30 Oct 2029 (+12 months)+12 mo
- IronbridgeEngland and Wales, Storage with solar or windAdded to the registerNew
- Ironbridge Green Energy CentreEngland and Wales, Storage with solar or windAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?