Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / Substation

Ironbridge 400kV Substation

England and Wales, National Grid Electricity Transmission

3projects in the register
1.3 GWstill to connect
0 MWof that with Gate 2 offers
0 MWconnected now

The queue at this substation

ProjectCustomerTechnologyQueued MWConnection dateGateStatus
Ironbridge Green Energy CentreIRONBRIDGE GREEN NG LIMITEDStorage with solar or wind40030 Oct 2029Gate 1Awaiting Consents
IronbridgeIGP SOLAR 16 LIMITEDStorage with solar or wind60030 Apr 2031Not statedScoping
ELMYA REDNALELMYA RPC UK REDNAL LIMITEDStorage30030 Oct 2034Gate 1Awaiting Consents

Left the register since January 2021: Ironbridge - New Connection (120 MW).

Recent changes

  • Ironbridge Green Energy CentreEngland and Wales, Storage with solar or windConnection date moved from 30 Oct 2032 to 30 Oct 2029 (−36 months)−36 mo
  • Ironbridge Green Energy CentreEngland and Wales, Storage with solar or windConnection date moved from 30 Oct 2029 to 30 Oct 2032 (+36 months)+36 mo
  • ELMYA REDNALEngland and Wales, StorageMarked as Gate 1
  • Ironbridge Green Energy CentreEngland and Wales, Storage with solar or windMarked as Gate 1
  • IronbridgeEngland and Wales, Storage with solar or windStage removed (0 MW from 30 Oct 2032)
  • IronbridgeEngland and Wales, Storage with solar or windRestructured from 1 stage (600 MW from 30 Oct 2032) to 2 stages (600 MW from 30 Apr 2031, 0 MW from 30 Oct 2032). First connection date −18 months−18 mo
  • Ironbridge Green Energy CentreEngland and Wales, Storage with solar or windCustomer changed from INNOVA RENEWABLES LIMITED to IRONBRIDGE GREEN NG LIMITED
  • IronbridgeEngland and Wales, Storage with solar or windConnection date moved from 30 Oct 2029 to 30 Oct 2032 (+36 months)+36 mo
  • Ironbridge - New ConnectionEngland and Wales, Storage with solar or windLeft the register (49.9 MW from 30 Jun 2025, 49.9 MW from 30 Jun 2026, 20.2 MW from 30 Dec 2026)120 MW
  • ELMYA REDNALEngland and Wales, StorageCustomer changed from ELMYA ENERGY UK 9 LIMITED to ELMYA RPC UK REDNAL LIMITED
  • IronbridgeEngland and Wales, Storage with solar or windSubstation name updated in the register (from Ironbridge GSP to Ironbridge 400kV Substation)
  • Ironbridge Green Energy CentreEngland and Wales, Storage with solar or windSubstation name updated in the register (from Ironbridge GSP to Ironbridge 400kV Substation)
  • ELMYA REDNALEngland and Wales, StorageCustomer changed from Alcemi Storage Developments 7 Ltd to ELMYA ENERGY UK 9 LIMITED
  • ELMYA REDNALEngland and Wales, StorageAdded to the registerNew
  • IronbridgeEngland and Wales, Storage with solar or windSubstation name updated in the register (from Ironbridge 400kV to Ironbridge GSP)
  • Ironbridge Green Energy CentreEngland and Wales, Storage with solar or windSubstation name updated in the register (from Ironbridge 400kV to Ironbridge GSP)
  • Ironbridge - New ConnectionEngland and Wales, Storage with solar or windSubstation name updated in the register (from Ironbridge 400kV to Ironbridge 400kV Substation)
  • IronbridgeEngland and Wales, Storage with solar or windSubstation name updated in the register (from Ironbridge to Ironbridge 400kV)
  • Ironbridge Green Energy CentreEngland and Wales, Storage with solar or windSubstation name updated in the register (from Ironbridge to Ironbridge 400kV)
  • Ironbridge - New ConnectionEngland and Wales, Storage with solar or windStage 3: Connection date moved from 30 Jun 2027 to 30 Dec 2026 (−6 months)−6 mo
  • Ironbridge Green Energy CentreEngland and Wales, Storage with solar or windConnection date moved from 30 Oct 2028 to 30 Oct 2029 (+12 months)+12 mo
  • IronbridgeEngland and Wales, Storage with solar or windAdded to the registerNew
  • Ironbridge Green Energy CentreEngland and Wales, Storage with solar or windAdded to the registerNew
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO