Ironbridge Green Energy Centre
- Connection date
- 30 Oct 2029
- Gate
- Gate 1
- Status
- Awaiting Consents
- Technology
- Storage + Solar
- Total capacity
- 400 MW
- Connected now
- 0 MW
- Still to connect
- 400 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001711
- In the register since
- December 2021
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 16 Oct 2026 registerConnection date moved from 30 Oct 2032 to 30 Oct 2029 (−36 months)
- 10 Oct 2026 registerConnection date moved from 30 Oct 2029 to 30 Oct 2032 (+36 months)
- 23 Dec 2025 registerMarked as Gate 1
- 28 Mar 2025 registerCustomer changed from INNOVA RENEWABLES LIMITED to IRONBRIDGE GREEN NG LIMITED
- 28 Jul 2023 registerSubstation name updated in the register (from Ironbridge GSP to Ironbridge 400kV Substation)
- 23 Dec 2022 registerSubstation name updated in the register (from Ironbridge 400kV to Ironbridge GSP)
- 28 Oct 2022 registerSubstation name updated in the register (from Ironbridge to Ironbridge 400kV)
- 28 Jan 2022 registerConnection date moved from 30 Oct 2028 to 30 Oct 2029 (+12 months)
- 31 Dec 2021 registerAdded to the register
Also at Ironbridge 400kV Substation
Substation view2 other projects, 1.3 GW still to connect at this substation in total.