Ironbridge
- Connection date
- 30 Apr 2031
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 600 MW
- Connected now
- 0 MW
- Still to connect
- 600 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001629
- In the register since
- December 2021
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Aug 2025 registerStage removed (0 MW from 30 Oct 2032)
- 29 Jul 2025 registerRestructured from 1 stage (600 MW from 30 Oct 2032) to 2 stages (600 MW from 30 Apr 2031, 0 MW from 30 Oct 2032). First connection date −18 months
- 31 Jan 2025 registerConnection date moved from 30 Oct 2029 to 30 Oct 2032 (+36 months)
- 28 Jul 2023 registerSubstation name updated in the register (from Ironbridge GSP to Ironbridge 400kV Substation)
- 23 Dec 2022 registerSubstation name updated in the register (from Ironbridge 400kV to Ironbridge GSP)
- 28 Oct 2022 registerSubstation name updated in the register (from Ironbridge to Ironbridge 400kV)
- 31 Dec 2021 registerAdded to the register
Also at Ironbridge 400kV Substation
Substation view2 other projects, 1.3 GW still to connect at this substation in total. 400 MW is due to connect here before this project’s connection date of 30 Apr 2031.