ELMYA REDNAL
- Connection date
- 30 Oct 2034
- Gate
- Gate 1
- Status
- Awaiting Consents
- Technology
- Storage
- Total capacity
- 300 MW
- Connected now
- 0 MW
- Still to connect
- 300 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002526
- In the register since
- May 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 20 Mar 2026 registerMarked as Gate 1
- 30 Jan 2024 registerCustomer changed from ELMYA ENERGY UK 9 LIMITED to ELMYA RPC UK REDNAL LIMITED
- 30 Jun 2023 registerCustomer changed from Alcemi Storage Developments 7 Ltd to ELMYA ENERGY UK 9 LIMITED
- 30 May 2023 registerAdded to the register
Also at Ironbridge 400kV Substation
Substation view2 other projects, 1.3 GW still to connect at this substation in total. 1 GW is due to connect here before this project’s connection date of 30 Oct 2034.