Creyke Beck 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Creyke Beck Battery 2 | CBB SPV LIMITED | Storage | 28.5 | 30 Jun 2028 | Not stated | Consents Approved |
| Hornsea Power Station 4 | ORSTED HORNSEA PROJECT FOUR LIMITED | Offshore wind | 2,600 | 30 Oct 2028 | Not stated | Scoping |
| CREYKE BECK | CLEAN AIR RENEWABLES LIMITED | Storage with solar or wind | 500 | 31 May 2033 | Not stated | Scoping |
| Creyke Beck PV & BESS Sub | BEFERLEAH ENERGY PARK LIMITED | Storage with solar or wind | 250 | 30 May 2035 | Not stated | Scoping |
| Bute Hydrogen Project 2 | HALDANE ENERGY PROJECT 2 LIMITED | Thermal (gas, biomass, waste) | 3,600 | 30 Oct 2035 | Gate 1 | Scoping |
| Flinton Road | FLINTON ROAD SOLAR LIMITED | Storage with solar or wind | 600 | 31 Oct 2039 | Not stated | Scoping |
Recent changes
- Bute Hydrogen Project 2England and Wales, Thermal (gas, biomass, waste)Connection date moved from 31 Oct 2035 to 30 Oct 2035 (1 day earlier)
- Bute Hydrogen Project 2England and Wales, Thermal (gas, biomass, waste)Marked as Gate 1
- Bute Hydrogen Project 2England and Wales, Thermal (gas, biomass, waste)Customer changed from Bute Hydrogen Project 2 Limited to HALDANE ENERGY PROJECT 2 LIMITED
- Bute Hydrogen Project 2England and Wales, Thermal (gas, biomass, waste)Technology changed from Gas (CCGT), Demand, Storage to Gas (CCGT)
- Flinton RoadEngland and Wales, Storage with solar or windCapacity changed from 221 MW to 600 MW
- Flinton RoadEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2037 to 31 Oct 2039 (+24 months)+24 mo
- Flinton RoadEngland and Wales, Storage with solar or windAdded to the registerNew
- Hornsea Power Station 4England and Wales, Offshore windStage 1: Connection date moved from 31 Oct 2028 to 30 Oct 2028 (1 day earlier)
- Hornsea Power Station 4England and Wales, Offshore windConnection point changed from Hornsea Offshore Platform 4 Substation to Creyke Beck 400kV Substation
- Hornsea Power Station 4England and Wales, Offshore windStage 1: Connection date moved from 1 Apr 2027 to 31 Oct 2028 (+19 months)+19 mo
- Hornsea Power Station 4England and Wales, Offshore windStage 2: Connection date moved from 31 Oct 2028 to 31 Oct 2029 (+12 months)+12 mo
- Creyke Beck Battery 2England and Wales, StorageCustomer changed from CREYKE BECK BATTERY 2 LIMITED to CBB SPV LIMITED
- Creyke Beck Battery 2England and Wales, StorageStatus changed from Scoping to Consents Approved
- Creyke Beck Battery 2England and Wales, StorageConnection date moved from 30 Oct 2034 to 30 Jun 2028 (−76 months)−76 mo
- Creyke Beck PV & BESS SubEngland and Wales, Storage with solar or windCustomer changed from O&G (SPV 55) Limited to BEFERLEAH ENERGY PARK LIMITED
- Bute Hydrogen Project 2England and Wales, Thermal (gas, biomass, waste)Added to the registerNew
- Creyke Beck PV & BESS SubEngland and Wales, Storage with solar or windCustomer changed from O&G Solar (SPV 40) Limited to O&G (SPV 55) Limited
- Creyke Beck PV & BESS SubEngland and Wales, Storage with solar or windAdded to the registerNew
- Creyke Beck Battery 2England and Wales, StorageAdded to the registerNew
- CREYKE BECKEngland and Wales, Storage with solar or windSubstation name updated in the register (from Creyke Beck 400kV to Creyke Beck 400kV Substation)
- Hornsea Power Station 4England and Wales, Offshore windSubstation name updated in the register (from Hornsea Offshore Platform 4 to Hornsea Offshore Platform 4 Substation)
- CREYKE BECKEngland and Wales, Storage with solar or windAdded to the registerNew
- Hornsea Power Station 4England and Wales, Offshore windStage 1: Connection date moved from 4 Jan 2027 to 1 Apr 2027 (+3 months)+3 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?