Cottam 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Tillbridge Solar | TILLBRIDGE SOLAR LIMITED | Storage with solar or wind | 500 | 27 Aug 2028 | Not stated | Scoping |
| Cottam Solar PV + BESS | COTTAM SOLAR PROJECT LIMITED | Storage with solar or wind | 600 | 1 Sep 2029 | Gate 2 | Consents Approved |
| Cottam | GATE BURTON ENERGY PARK LIMITED | Storage with solar or wind | 500 | 31 Oct 2029 | Not stated | Consents Approved |
| Cottam PV & BESS | O&G Solar (SPV 44) Limited | Storage with solar or wind | 500 | 31 Oct 2033 | Not stated | Scoping |
| CDCL | Uniper UK Limited | Thermal (gas, biomass, waste) | 0 | Connected | Not stated | Built |
Left the register since January 2021: Cottam (0 MW).
Recent changes
- Cottam Solar PV + BESSEngland and Wales, Storage with solar or windGiven a Gate 2 connection offerGate 2
- CDCLEngland and Wales, Thermal (gas, biomass, waste)Customer changed from C.GEN Killingholme Limited to Uniper UK Limited
- CDCLEngland and Wales, Thermal (gas, biomass, waste)Customer changed from Uniper UK Limited to C.GEN Killingholme Limited
- Cottam PV & BESSEngland and Wales, Storage with solar or windRenamed from Cottam PV & BESS Sub
- Tillbridge SolarEngland and Wales, Storage with solar or windConnection date moved from 1 Aug 2028 to 27 Aug 2028 (+1 month)+1 mo
- CottamEngland and Wales, Storage with solar or windStage 1: Status changed from Scoping to Consents Approved
- CottamEngland and Wales, Storage with solar or windStage 2: Status changed from Scoping to Consents Approved
- Cottam Solar PV + BESSEngland and Wales, Storage with solar or windStatus changed from Scoping to Consents Approved
- Tillbridge SolarEngland and Wales, Storage with solar or windConnection date moved from 1 Oct 2027 to 1 Aug 2028 (+10 months)+10 mo
- Cottam PV & BESSEngland and Wales, Storage with solar or windCustomer changed from O&G Solar (SPV 37) Limited to O&G Solar (SPV 44) Limited
- CottamEngland and Wales, Thermal (gas, biomass, waste)Left the register (0 MW)0 MW
- Cottam PV & BESSEngland and Wales, Storage with solar or windAdded to the registerNew
- Tillbridge SolarEngland and Wales, Storage with solar or windRenamed from Greta II
- CottamEngland and Wales, Storage with solar or windRenamed from Gate Burton Energy Park
- CottamEngland and Wales, Storage with solar or windRenamed from Cottam
- CottamEngland and Wales, Storage with solar or windStage 1: Technology changed from Solar to Storage, Solar
- CottamEngland and Wales, Storage with solar or windStage 2: Technology changed from Solar to Storage, Solar
- Cottam Solar PV + BESSEngland and Wales, Storage with solar or windSubstation name updated in the register (from Cottam 400kV to Cottam 400kV Substation)
- Tillbridge SolarEngland and Wales, Storage with solar or windCustomer changed from GRETA II LIMITED to TILLBRIDGE SOLAR LIMITED
- CottamEngland and Wales, Storage with solar or windCustomer changed from WB ENERGY PARK LIMITED to GATE BURTON ENERGY PARK LIMITED
- CDCLEngland and Wales, Thermal (gas, biomass, waste)Substation name updated in the register (from Cottam 400kV to Cottam 400kV Substation)
- CottamEngland and Wales, Storage with solar or windSubstation name updated in the register (from Cottam 400kV to Cottam 400kV Substation)
- Tillbridge SolarEngland and Wales, Storage with solar or windSubstation name updated in the register (from Cottam 400kV to Cottam 400kV Substation)
- CottamEngland and Wales, Thermal (gas, biomass, waste)Substation name updated in the register (from Cottam 400kV to Cottam 400kV Substation)
- Tillbridge SolarEngland and Wales, Storage with solar or windCustomer changed from GRETA I LIMITED to GRETA II LIMITED
- Tillbridge SolarEngland and Wales, Storage with solar or windConnection point changed from High Marnham Substation 275kV to Cottam 400kV
- Cottam Solar PV + BESSEngland and Wales, Storage with solar or windAdded to the registerNew
- CottamEngland and Wales, Storage with solar or windAdded to the registerNew
- Tillbridge SolarEngland and Wales, Storage with solar or windConnection date moved from 10 Jan 2027 to 1 Oct 2027 (+9 months)+9 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?