Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / England and Wales
Connection date
31 Oct 2029
Gate
Not stated
Status
Consents Approved
Planning consent
Granted 12 Jul 2024
Gate Burton Energy Park (EN010131) · Source: Planning Inspectorate
Technology
Storage + Solar
Total capacity
500 MW
Connected now
0 MW
Still to connect
500 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Direct Connection
Region
England and Wales
Project number
PRO-001502
In the register since
June 2021

What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?

Stages

StageConnected MWAdds MWCumulative MWDateGateStatus
1025025031 Oct 2029Not statedConsents Approved
2025050030 Jul 2030Not statedConsents Approved

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 26 Nov 2024 register
    Stage 1: Status changed from Scoping to Consents Approved
  • 26 Nov 2024 register
    Stage 2: Status changed from Scoping to Consents Approved
  • 31 Mar 2023 register
    Renamed from Gate Burton Energy Park
  • 28 Feb 2023 register
    Renamed from Cottam
  • 28 Feb 2023 register
    Stage 1: Technology changed from Solar to Storage, Solar
  • 28 Feb 2023 register
    Stage 2: Technology changed from Solar to Storage, Solar
  • 29 Apr 2022 register
    Customer changed from WB ENERGY PARK LIMITED to GATE BURTON ENERGY PARK LIMITED
  • 30 Mar 2022 register
    Substation name updated in the register (from Cottam 400kV to Cottam 400kV Substation)
  • 29 Jun 2021 register
    Added to the register

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO

Planning consent

The planning decision for this project, from the Planning Inspectorate. NESO’s status can lag behind planning decisions, so the two may differ.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.