Merlin Offshore Wind Farm
- Connection date
- 31 Oct 2031 +36 months since 9 Dec
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Offshore wind
- Total capacity
- 300 MW
- Connected now
- 0 MW
- Still to connect
- 300 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001728
- In the register since
- January 2022
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 27 Oct 2026 registerConnection date moved from 30 Oct 2031 to 31 Oct 2031 (1 day later)
- 10 Oct 2026 registerConnection date moved from 1 Nov 2028 to 30 Oct 2031 (+36 months)
- 9 Dec 2025 registerMarked as Gate 1
- 30 Mar 2022 registerSubstation name updated in the register (from Alverdiscott 400kV to Alverdiscott 400kV Substation)
- 28 Jan 2022 registerAdded to the register
Also at Alverdiscott 400kV Substation
Substation view14 other projects, 13.3 GW still to connect at this substation in total. 350 MW is due to connect here before this project’s connection date of 31 Oct 2031.
- Petroc Offshore Wind FarmBLUEFLOAT ENERGY UK HOLDINGS LIMITED, Offshore wind, Gate 1Mar 2029300 MW
- AlverdiscottPIVOTED POWER LLP, Storage, Gate 1Aug 2031100 MW
- Celtic 2 Offshore Wind FarmRWE Offshore Wind, Offshore wind, Gate 1Oct 20311 GW
- Gwynt Glas Offshore Wind FarmGWYNT GLAS OFFSHORE WIND FARM LIMITED, Offshore wind, Gate 1Oct 2031300 MW
- Merlin 2 Offshore WindfarmOFFSHORE WIND LIMITED, Offshore wind, Gate 1Oct 20311.5 GW
- Morwind 300Morwind Ltd, Offshore wind, Not statedOct 2031300 MW
- Cormoran Offshore Wind FarmSouth West Wind Holdco Limited, Offshore wind, Not statedDec 20361 GW
- Equinor Celtic Sea 1EQUINOR NEW ENERGY LIMITED, Offshore wind, Gate 1Dec 20361 GW