Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / England and Wales

Petroc Offshore Wind Farm

BLUEFLOAT ENERGY UK HOLDINGS LIMITED at Alverdiscott 400kV Substation

Connection date
31 Mar 2029
Gate
Gate 1
Status
Scoping
Technology
Offshore wind
Total capacity
300 MW
Connected now
0 MW
Still to connect
300 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Direct Connection
Region
England and Wales
Project number
PRO-001661
In the register since
August 2021

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 27 Oct 2026 register
    Connection date moved from 31 Mar 2026 to 31 Mar 2029 (+36 months)
  • 16 Oct 2026 register
    Connection date moved from 6 Dec 2036 to 31 Mar 2026 (−128 months)
  • 10 Oct 2026 register
    Connection date moved from 31 Mar 2029 to 6 Dec 2036 (+92 months)
  • 14 Jul 2026 register
    Marked as Gate 1
  • 1 May 2026 register
    Customer changed from SCARABEN OFFSHORE WIND FARM LIMITED to BLUEFLOAT ENERGY UK HOLDINGS LIMITED
  • 29 Jul 2025 register
    Customer changed from BLUEFLOAT ENERGY UK HOLDINGS LIMITED to SCARABEN OFFSHORE WIND FARM LIMITED
  • 30 Mar 2022 register
    Connection point changed from Alverdiscott to Alverdiscott 400kV Substation
  • 25 Feb 2022 register
    Renamed from Dewnens Floating Offshore Wind Farm
  • 31 Aug 2021 register
    Added to the register

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO