Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

OFFSHORE WIND LIMITED

Customer named in the TEC register

2projects in the register
1.8 GWstill to connect
0 MWof that with Gate 2 offers
0 MWconnected now

Projects

ProjectConnection siteTechnologyQueued MWConnection dateGateStatus
Merlin 2 Offshore WindfarmAlverdiscott 400kV SubstationOffshore wind1,50031 Oct 2031Gate 1Scoping
Merlin Offshore Wind FarmAlverdiscott 400kV SubstationOffshore wind30031 Oct 2031 +36 moGate 1Scoping

Left the register since January 2021: North Sea Offshore Wind Farm (1.5 GW).

Recent changes

  • Merlin Offshore Wind FarmEngland and Wales, Offshore windConnection date moved from 30 Oct 2031 to 31 Oct 2031 (1 day later)
  • Merlin Offshore Wind FarmEngland and Wales, Offshore windConnection date moved from 1 Nov 2028 to 30 Oct 2031 (+36 months)+36 mo
  • Merlin 2 Offshore WindfarmEngland and Wales, Offshore windMarked as Gate 1
  • Merlin Offshore Wind FarmEngland and Wales, Offshore windMarked as Gate 1
  • North Sea Offshore Wind FarmNorth Scotland, Offshore windLeft the register (1,500 MW from 31 Oct 2033)1,500 MW
  • Merlin 2 Offshore WindfarmEngland and Wales, Offshore windAdded to the registerNew
  • Merlin Offshore Wind FarmEngland and Wales, Offshore windSubstation name updated in the register (from Alverdiscott 400kV to Alverdiscott 400kV Substation)
  • Merlin Offshore Wind FarmEngland and Wales, Offshore windAdded to the registerNew
  • North Sea Offshore Wind FarmNorth Scotland, Offshore windAdded to the registerNew
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO