OFFSHORE WIND LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Merlin 2 Offshore Windfarm | Alverdiscott 400kV Substation | Offshore wind | 1,500 | 31 Oct 2031 | Gate 1 | Scoping |
| Merlin Offshore Wind Farm | Alverdiscott 400kV Substation | Offshore wind | 300 | 31 Oct 2031 +36 mo | Gate 1 | Scoping |
Left the register since January 2021: North Sea Offshore Wind Farm (1.5 GW).
Recent changes
- Merlin Offshore Wind FarmEngland and Wales, Offshore windConnection date moved from 30 Oct 2031 to 31 Oct 2031 (1 day later)
- Merlin Offshore Wind FarmEngland and Wales, Offshore windConnection date moved from 1 Nov 2028 to 30 Oct 2031 (+36 months)+36 mo
- Merlin 2 Offshore WindfarmEngland and Wales, Offshore windMarked as Gate 1
- Merlin Offshore Wind FarmEngland and Wales, Offshore windMarked as Gate 1
- North Sea Offshore Wind FarmNorth Scotland, Offshore windLeft the register (1,500 MW from 31 Oct 2033)1,500 MW
- Merlin 2 Offshore WindfarmEngland and Wales, Offshore windAdded to the registerNew
- Merlin Offshore Wind FarmEngland and Wales, Offshore windSubstation name updated in the register (from Alverdiscott 400kV to Alverdiscott 400kV Substation)
- Merlin Offshore Wind FarmEngland and Wales, Offshore windAdded to the registerNew
- North Sea Offshore Wind FarmNorth Scotland, Offshore windAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?