Thorpe Marsh 1 (Tertiary)
ENSO GREEN HOLDINGS I LIMITED at Thorpe Marsh 400kV Substation
- Connection date
- 30 Oct 2028
- Gate
- Not stated
- Status
- Consents Approved
- Technology
- Storage + Solar
- Total capacity
- 57 MW
- Connected now
- 0 MW
- Still to connect
- 57 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000470
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Apr 2025 registerCustomer changed from ENSO GREEN HOLDINGS LIMITED to ENSO GREEN HOLDINGS I LIMITED
- 28 Mar 2025 registerConnection date moved from 6 Aug 2025 to 30 Oct 2028 (+39 months)
- 28 Feb 2025 registerRestructured from 2 stages (49.9 MW from 31 Oct 2024, 7.1 MW from 31 Oct 2026) to 1 stage (57 MW from 6 Aug 2025). First connection date +9 months
- 28 Nov 2023 registerConnection point changed from Thorpe Marsh GSP to Thorpe Marsh 400kV Substation
- 23 Dec 2022 registerSubstation name updated in the register (from Thorpe Marsh to Thorpe Marsh GSP)
Also at Thorpe Marsh 400kV Substation
Substation view3 other projects, 2.7 GW still to connect at this substation in total. 1.4 GW is due to connect here before this project’s connection date of 30 Oct 2028.