BLUEFLOAT ENERGY UK HOLDINGS LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Petroc Offshore Wind Farm | Alverdiscott 400kV Substation | Offshore wind | 300 | 31 Mar 2029 | Gate 1 | Scoping |
| Petroc Extension Offshore Wind Farm | Alverdiscott 400kV Substation | Offshore wind | 1,000 | 6 Dec 2036 | Not stated | Scoping |
Recent changes
- Petroc Offshore Wind FarmEngland and Wales, Offshore windConnection date moved from 31 Mar 2026 to 31 Mar 2029 (+36 months)+36 mo
- Petroc Offshore Wind FarmEngland and Wales, Offshore windConnection date moved from 6 Dec 2036 to 31 Mar 2026 (−128 months)−128 mo
- Petroc Offshore Wind FarmEngland and Wales, Offshore windConnection date moved from 31 Mar 2029 to 6 Dec 2036 (+92 months)+92 mo
- Petroc Offshore Wind FarmEngland and Wales, Offshore windMarked as Gate 1
- Petroc Extension Offshore Wind FarmEngland and Wales, Offshore windCustomer changed from SCARABEN OFFSHORE WIND FARM LIMITED to BLUEFLOAT ENERGY UK HOLDINGS LIMITED
- Petroc Offshore Wind FarmEngland and Wales, Offshore windCustomer changed from SCARABEN OFFSHORE WIND FARM LIMITED to BLUEFLOAT ENERGY UK HOLDINGS LIMITED
- Petroc Extension Offshore Wind FarmEngland and Wales, Offshore windCustomer changed from BLUEFLOAT ENERGY UK HOLDINGS LIMITED to SCARABEN OFFSHORE WIND FARM LIMITED
- Petroc Offshore Wind FarmEngland and Wales, Offshore windCustomer changed from BLUEFLOAT ENERGY UK HOLDINGS LIMITED to SCARABEN OFFSHORE WIND FARM LIMITED
- Petroc Extension Offshore Wind FarmEngland and Wales, Offshore windAdded to the registerNew
- Petroc Offshore Wind FarmEngland and Wales, Offshore windConnection point changed from Alverdiscott to Alverdiscott 400kV Substation
- Petroc Offshore Wind FarmEngland and Wales, Offshore windRenamed from Dewnens Floating Offshore Wind Farm
- Petroc Offshore Wind FarmEngland and Wales, Offshore windAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?