Plas Power Estate North Tertiary
- Connection date
- 31 May 2028
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 57 MW
- Connected now
- 0 MW
- Still to connect
- 57 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001050
- In the register since
- August 2021
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Jul 2025 registerConnection date moved from 1 Aug 2026 to 31 May 2028 (+22 months)
- 29 Dec 2023 registerTechnology changed from Solar to Storage, Solar
- 28 Jul 2023 registerSubstation name updated in the register (from Legacy GSP to Legacy 400kV Substation)
- 30 Jun 2023 registerConnection date moved from 31 May 2024 to 1 Aug 2026 (+26 months)
- 23 Dec 2022 registerSubstation name updated in the register (from Legacy to Legacy GSP)
- 29 Jul 2022 registerCustomer changed from LIGHTSOURCE RENEWABLE UK DEVELOPMENT LIMITED to LIGHTSOURCE SPV 192 LIMITED
- 30 Jun 2022 registerConnection date moved from 31 May 2023 to 31 May 2024 (+12 months)
- 31 Aug 2021 registerAdded to the register
Also at Legacy 400kV Substation
Substation view3 other projects, 1.7 GW still to connect at this substation in total. 457 MW is due to connect here before this project’s connection date of 31 May 2028.