Legacy Tertiary Connection
- Connection date
- 31 Aug 2024
- Gate
- Not stated
- Status
- Consents Approved
- Technology
- Storage
- Total capacity
- 57 MW
- Connected now
- 0 MW
- Still to connect
- 57 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001171
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 28 Feb 2023 registerRenamed from Legacy Tertiary Connection (formerly Legacy Gas)
- 28 Feb 2023 registerStatus changed from Scoping to Consents Approved
- 28 Feb 2023 registerTechnology changed from Gas engines to Storage
- 28 Sep 2021 registerCapacity changed from 49.9 MW to 57 MW
- 28 Sep 2021 registerConnection date moved from 1 Sep 2023 to 31 Aug 2024 (+12 months)
- 30 Apr 2021 registerRenamed from Legacy Gas
- 26 Feb 2021 registerConnection date moved from 9 Jan 2023 to 1 Sep 2023 (+8 months)
Also at Legacy 400kV Substation
Substation view3 other projects, 1.7 GW still to connect at this substation in total.