LIGHTSOURCE SPV 192 LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Plas Power Estate North Tertiary | Legacy 400kV Substation | Storage with solar or wind | 57 | 31 May 2028 | Not stated | Scoping |
Recent changes
- Plas Power Estate North TertiaryEngland and Wales, Storage with solar or windConnection date moved from 1 Aug 2026 to 31 May 2028 (+22 months)+22 mo
- Plas Power Estate North TertiaryEngland and Wales, Storage with solar or windTechnology changed from Solar to Storage, Solar
- Plas Power Estate North TertiaryEngland and Wales, Storage with solar or windSubstation name updated in the register (from Legacy GSP to Legacy 400kV Substation)
- Plas Power Estate North TertiaryEngland and Wales, Storage with solar or windConnection date moved from 31 May 2024 to 1 Aug 2026 (+26 months)+26 mo
- Plas Power Estate North TertiaryEngland and Wales, Storage with solar or windSubstation name updated in the register (from Legacy to Legacy GSP)
- Plas Power Estate North TertiaryEngland and Wales, Storage with solar or windCustomer changed from LIGHTSOURCE RENEWABLE UK DEVELOPMENT LIMITED to LIGHTSOURCE SPV 192 LIMITED
- Plas Power Estate North TertiaryEngland and Wales, Storage with solar or windConnection date moved from 31 May 2023 to 31 May 2024 (+12 months)+12 mo
- Plas Power Estate North TertiaryEngland and Wales, Storage with solar or windAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?