Capenhurst
ENSO GREEN HOLDINGS Q LIMITED at Capenhurst 275kV Substation
- Connection date
- 14 Sep 2033 −1 month since 9 Dec
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 400 MW
- Connected now
- 0 MW
- Still to connect
- 400 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000540
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 10 Oct 2026 registerConnection date moved from 30 Sep 2033 to 14 Sep 2033 (−1 month)
- 17 Jul 2026 registerCustomer changed from ENSO GREEN HOLDINGS LIMITED to ENSO GREEN HOLDINGS Q LIMITED
- 24 Mar 2026 registerCustomer changed from ENSO GREEN HOLDINGS Q LIMITED to ENSO GREEN HOLDINGS LIMITED
- 20 Jan 2026 registerCustomer changed from ENSO GREEN HOLDINGS LIMITED to ENSO GREEN HOLDINGS Q LIMITED
- 9 Dec 2025 registerMarked as Gate 1
- 24 Dec 2024 registerConnection date moved from 31 Oct 2030 to 30 Sep 2033 (+35 months)
- 26 Nov 2024 registerStatus changed from Awaiting Consents to Scoping
- 26 Nov 2024 registerStage removed (49.9 MW from 31 Oct 2025)
- 26 Nov 2024 registerStage removed (7.1 MW from 31 Oct 2027)
- 31 May 2024 registerRenamed from Capenhurst (Tertiary)
- 31 May 2024 registerNew stage added (400 MW from 31 Oct 2030)
- 31 May 2022 registerStage 1: Technology changed from Hybrid to Storage, Solar
- 31 May 2022 registerStage 2: Technology changed from Hybrid to Storage, Solar
- 30 Mar 2022 registerSubstation name updated in the register (from Capenhurst 275kV to Capenhurst 275kV Substation)
- 28 Jan 2022 registerStage 1: Technology changed from Storage, Solar to Hybrid
- 28 Jan 2022 registerStage 2: Technology changed from Storage, Solar to Hybrid
Also at Capenhurst 275kV Substation
Substation view3 other projects, 400 MW still to connect at this substation in total.