Capenhurst 275KV Substation
- Connection date
- Connected
- Gate
- Not stated
- Status
- Built
- Technology
- Storage
- Total capacity
- 100 MW
- Connected now
- 100 MW
- Still to connect
- 0 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001349
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 30 Jun 2022 register100 MW now connected
- 30 Jun 2022 registerStatus changed from Scoping to Built
- 29 Apr 2022 registerConnection date moved from 28 Feb 2022 to 28 Apr 2022 (+2 months)
- 30 Mar 2022 registerSubstation name updated in the register (from Capenhurst 275kV to Capenhurst 275kV Substation)
- 28 Sep 2021 registerCapacity changed from 99.8 MW to 100 MW
- 30 Jul 2021 registerCustomer changed from ZENOBE ENERGY LIMITED to Zenobe Capenhurst Limited
- 30 Jul 2021 registerCapacity changed from 49.9 MW to 99.8 MW
Also at Capenhurst 275kV Substation
Substation view3 other projects, 400 MW still to connect at this substation in total.