Capenhurst Tertiary Connection
- Connection date
- Connected
- Gate
- Not stated
- Status
- Built
- Technology
- Storage
- Total capacity
- 57 MW
- Connected now
- 57 MW
- Still to connect
- 0 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001028
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 12 Jun 2026 register57 MW now connected
- 12 Jun 2026 registerStatus changed from Consents Approved to Built
- 28 Feb 2023 registerRenamed from Capenhurst Tertiary Connection (formerly Capenhurst Gas)
- 28 Feb 2023 registerTechnology changed from Gas (CCGT) to Storage
- 30 Mar 2022 registerSubstation name updated in the register (from Capenhurst 275kV to Capenhurst 275kV Substation)
- 28 Sep 2021 registerCapacity changed from 49.5 MW to 57 MW
- 28 Sep 2021 registerConnection date moved from 30 Oct 2022 to 31 Oct 2023 (+12 months)
- 30 Apr 2021 registerRenamed from Capenhurst Gas
Also at Capenhurst 275kV Substation
Substation view3 other projects, 400 MW still to connect at this substation in total.