Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

ENSO GREEN HOLDINGS Q LIMITED

Customer named in the TEC register

3projects in the register
857 MWstill to connect
0 MWof that with Gate 2 offers
0 MWconnected now

Projects

ProjectConnection siteTechnologyQueued MWConnection dateGateStatus
Capenhurst TertiaryCapenhurst 400kV SubstationStorage with solar or wind5731 Oct 2027 −24 moGate 1Scoping
RassauRassau 400kV SubstationStorage with solar or wind40031 Oct 2030Gate 1Scoping
CapenhurstCapenhurst 275kV SubstationStorage with solar or wind40014 Sep 2033 −1 moGate 1Scoping

Recent changes

  • CapenhurstEngland and Wales, Storage with solar or windConnection date moved from 30 Sep 2033 to 14 Sep 2033 (−1 month)−1 mo
  • Capenhurst TertiaryEngland and Wales, Storage with solar or windConnection date moved from 30 Oct 2029 to 31 Oct 2027 (−24 months)−24 mo
  • CapenhurstEngland and Wales, Storage with solar or windCustomer changed from ENSO GREEN HOLDINGS LIMITED to ENSO GREEN HOLDINGS Q LIMITED
  • Capenhurst TertiaryEngland and Wales, Storage with solar or windMarked as Gate 1
  • CapenhurstEngland and Wales, Storage with solar or windCustomer changed from ENSO GREEN HOLDINGS Q LIMITED to ENSO GREEN HOLDINGS LIMITED
  • CapenhurstEngland and Wales, Storage with solar or windCustomer changed from ENSO GREEN HOLDINGS LIMITED to ENSO GREEN HOLDINGS Q LIMITED
  • RassauEngland and Wales, Storage with solar or windCustomer changed from ENSO GREEN HOLDINGS LIMITED to ENSO GREEN HOLDINGS Q LIMITED
  • CapenhurstEngland and Wales, Storage with solar or windMarked as Gate 1
  • RassauEngland and Wales, Storage with solar or windMarked as Gate 1
  • Capenhurst TertiaryEngland and Wales, Storage with solar or windRestructured from 2 stages (49.9 MW from 31 Oct 2025, 7.1 MW from 31 Oct 2027) to 1 stage (57 MW from 30 Oct 2029). First connection date +48 months+48 mo
  • Capenhurst TertiaryEngland and Wales, Storage with solar or windCustomer changed from ENSO GREEN HOLDINGS Q LIMITED to ENSO GREEN HOLDINGS LIMITED
  • Capenhurst TertiaryEngland and Wales, Storage with solar or windCustomer changed from ENSO GREEN HOLDINGS LIMITED to ENSO GREEN HOLDINGS Q LIMITED
  • CapenhurstEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2030 to 30 Sep 2033 (+35 months)+35 mo
  • CapenhurstEngland and Wales, Storage with solar or windStatus changed from Awaiting Consents to Scoping
  • CapenhurstEngland and Wales, Storage with solar or windStage removed (49.9 MW from 31 Oct 2025)
  • CapenhurstEngland and Wales, Storage with solar or windStage removed (7.1 MW from 31 Oct 2027)
  • Capenhurst TertiaryEngland and Wales, Storage with solar or windAdded to the registerNew
  • CapenhurstEngland and Wales, Storage with solar or windRenamed from Capenhurst (Tertiary)
  • CapenhurstEngland and Wales, Storage with solar or windNew stage added (400 MW from 31 Oct 2030)
  • Capenhurst TertiaryEngland and Wales, Storage with solar or windLeft the register (400 MW from 31 Oct 2030)400 MW
  • Capenhurst TertiaryEngland and Wales, Storage with solar or windAdded to the registerNew
  • RassauEngland and Wales, Storage with solar or windAdded to the registerNew
  • CapenhurstEngland and Wales, Storage with solar or windStage 1: Technology changed from Hybrid to Storage, Solar
  • CapenhurstEngland and Wales, Storage with solar or windStage 2: Technology changed from Hybrid to Storage, Solar
  • CapenhurstEngland and Wales, Storage with solar or windSubstation name updated in the register (from Capenhurst 275kV to Capenhurst 275kV Substation)
  • CapenhurstEngland and Wales, Storage with solar or windStage 1: Technology changed from Storage, Solar to Hybrid
  • CapenhurstEngland and Wales, Storage with solar or windStage 2: Technology changed from Storage, Solar to Hybrid
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO