AWEL Y MOR OFFSHORE WIND FARM LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Awel Y Mor | Bodelwyddan 400kV Substation | Offshore wind | 1,100 | 1 Mar 2030 +35 mo | Not stated | Scoping |
Recent changes
- Awel Y MorEngland and Wales, Offshore windRestructured from 2 stages (574 MW from 1 Apr 2027, 526 MW from 1 Apr 2028) to 1 stage (1,100 MW from 1 Mar 2030). First connection date +35 months+35 mo
- Awel Y MorEngland and Wales, Offshore windRenamed from Awel Y Mor Extension
- Awel Y MorEngland and Wales, Offshore windRestructured from 1 stage (1,100 MW from 1 Apr 2027) to 2 stages (574 MW from 1 Apr 2027, 526 MW from 1 Apr 2028)
- Awel Y MorEngland and Wales, Offshore windConnection point changed from Gwynt y Mor 132/33kV Offshore Substation to Bodelwyddan 400kV Substation
- Awel Y MorEngland and Wales, Offshore windTransmission owner changed from OFTO to NGET
- Awel Y MorEngland and Wales, Offshore windCapacity changed from 580 MW to 1,100 MW
- Awel Y MorEngland and Wales, Offshore windConnection date moved from 4 Jan 2027 to 1 Apr 2027 (+3 months)+3 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?