Enderby Tertiary
- Connection date
- 31 Aug 2028 +13 months since 9 Dec
- Gate
- Gate 2
- Status
- Consents Approved
- Technology
- Solar
- Total capacity
- 57 MW
- Connected now
- 0 MW
- Still to connect
- 57 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000430
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 16 Oct 2026 registerGiven a Gate 2 connection offer
- 13 Oct 2026 registerConnection date moved from 1 Aug 2027 to 31 Aug 2028 (+13 months)
- 5 Oct 2026 registerStatus changed from Scoping to Consents Approved
- 24 Dec 2024 registerConnection date moved from 1 May 2024 to 1 Aug 2027 (+39 months)
- 31 May 2024 registerTechnology changed from Thermal to Solar
- 30 Jun 2023 registerSubstation name updated in the register (from Enderby 400kV to Enderby 400kV Substation)
- 29 Jun 2021 registerCustomer changed from ENDERBY SOLAR LIMITED to CLUMP FARM SOLAR LIMITED
- 26 Feb 2021 registerConnection date moved from 5 Jan 2024 to 1 May 2024 (+4 months)
Also at Enderby 400kV Substation
Substation view3 other projects, 2.1 GW still to connect at this substation in total.