Rugby High Impact Green Energy Hub (HIGEH) 1
- Connection date
- 30 Oct 2037 +36 months since 9 Dec
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Nuclear + Solar + Onshore wind
- Total capacity
- 1,000 MW
- Connected now
- 0 MW
- Still to connect
- 1,000 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-003626
- In the register since
- November 2023
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 27 Oct 2026 registerConnection date moved from 31 Oct 2033 to 30 Oct 2037 (+48 months)
- 16 Oct 2026 registerConnection date moved from 30 Oct 2037 to 31 Oct 2033 (−48 months)
- 10 Oct 2026 registerConnection date moved from 31 Oct 2034 to 30 Oct 2037 (+36 months)
- 27 Feb 2026 registerMarked as Gate 1
- 27 Feb 2024 registerStatus changed from Awaiting Consents to Scoping
- 28 Nov 2023 registerAdded to the register
Also at Enderby 400kV Substation
Substation view3 other projects, 2.1 GW still to connect at this substation in total. 1.1 GW is due to connect here before this project’s connection date of 30 Oct 2037.