Enderby (Akira)
- Connection date
- Connected
- Gate
- Not stated
- Status
- Built
- Technology
- Storage
- Total capacity
- 57 MW
- Connected now
- 57 MW
- Still to connect
- 0 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000426
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 30 Sep 2025 register57 MW now connected
- 30 May 2025 registerStatus changed from Consents Approved to Built
- 26 Nov 2024 registerConnection date moved from 31 Aug 2023 to 9 Dec 2024 (+15 months)
- 29 Dec 2023 registerRenamed from Enderby
- 28 Feb 2023 registerCustomer changed from HB197END Limited to ENDERBY BATTERY STORAGE LIMITED
- 28 Feb 2023 registerSubstation name updated in the register (from Enderby GSP to Enderby 400kV Substation)
- 28 Feb 2023 registerStatus changed from Scoping to Consents Approved
- 23 Dec 2022 registerSubstation name updated in the register (from Enderby to Enderby GSP)
- 28 Sep 2021 registerCapacity changed from 49.9 MW to 57 MW
- 28 Sep 2021 registerConnection date moved from 1 Sep 2023 to 31 Aug 2023 (1 day earlier)
- 26 Feb 2021 registerConnection date moved from 9 Jan 2023 to 1 Sep 2023 (+8 months)
Also at Enderby 400kV Substation
Substation view3 other projects, 2.1 GW still to connect at this substation in total.