CLUMP FARM SOLAR LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Enderby Tertiary | Enderby 400kV Substation | Solar | 57 | 31 Aug 2028 +13 mo | Gate 2 | Consents Approved |
Recent changes
- Enderby TertiaryEngland and Wales, SolarGiven a Gate 2 connection offerGate 2
- Enderby TertiaryEngland and Wales, SolarConnection date moved from 1 Aug 2027 to 31 Aug 2028 (+13 months)+13 mo
- Enderby TertiaryEngland and Wales, SolarStatus changed from Scoping to Consents Approved
- Enderby TertiaryEngland and Wales, SolarConnection date moved from 1 May 2024 to 1 Aug 2027 (+39 months)+39 mo
- Enderby TertiaryEngland and Wales, SolarTechnology changed from Thermal to Solar
- Enderby TertiaryEngland and Wales, SolarSubstation name updated in the register (from Enderby 400kV to Enderby 400kV Substation)
- Enderby TertiaryEngland and Wales, SolarCustomer changed from ENDERBY SOLAR LIMITED to CLUMP FARM SOLAR LIMITED
- Enderby TertiaryEngland and Wales, SolarConnection date moved from 5 Jan 2024 to 1 May 2024 (+4 months)+4 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?