QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.

BALGOWAN SOLAR & BESS

At BURGHMUIR

SSEN Embedded Capacity Register, November 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
31 Oct 2033
Status
Accepted to connect
Customer
Not stated
Site name
BALGOWAN SOLAR & BESS
Address
BALGOWAN SOLAR & BESS, BALGOWAN METHVEN, PERTH, PERTHSHIRE AND KINROSS, PH1 3RQ
Grid reference
Easting 298996, northing 722662
Licence area
North of Scotland (SHEPD)
Grid supply point
BURGHMUIR
Bulk supply point
Not stated
Primary substation
Not stated
Connection voltage
33 kV
Technology group
Solar
Energy source 1
SOLAR, PHOTOVOLTAIC: 99.8 MW registered
Registered capacity
99.8 MW
Change to maximum export capacity
49.9 MW
Change to maximum import capacity
49.9 MW
Flexible connection
Not stated
In a connection queue
Not published by SSEN
Date accepted
13 May 2024
Date connected
Not stated
Distribution reinforcement reference
Not published by SSEN
Transmission reinforcement reference
Not published by SSEN
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
10 Feb 2026
Tracked since
June 2024 edition

Change history

Tracked since the June 2024 edition, across 30 editions.

Changes to the details QueueWatch tracks, newest first.

  • November 2025 edition
    Target energisation date stated as 31 Oct 2033 (not stated in the October 2025 edition)

Also at BURGHMUIR

GSP view

5 other sites at this grid supply point in the November 2026 edition. In all, the sites here total 291 MW: 51 MW connected, 240 MW accepted to connect.

  • DUPPLIN SOLAR 75MW BESS&SOLARSolar, BURGHMUIR GRID primaryAccepted75 MW
  • KINNON PARKCERTUS UTILITY CONSULTING LTD, Solar, BURGHMUIR GRID primaryAccepted56.925 MW
  • Site not namedName not shown, Storage, BURGHMUIR GRID primaryConnected49.4 MW
  • PERTH ROYAL INFIRMARYWGM CONSULTING ENGINEERS, Other or not stated, BURGHMUIR GRID primaryAccepted8 MW
  • PITHEAVLISAVIVA CENTRAL SERVICES UK LIMITED, Storage, BURGHMUIR GRID primaryConnected1.393 MW
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?