Distribution / SSEN / Grid supply point

FIDDES

Grid supply point in North of Scotland (SHEPD)

SSEN Embedded Capacity Register, November 2026 edition

19sites of 1 MW and over
456 MWcapacity
86 MWconnected (9 sites)
370 MWaccepted to connect (10 sites)

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Solar5182 MW5 MW177 MW
Storage3133 MW–133 MW
Wind1091 MW81 MW10 MW
Other or not stated149.9 MW–49.9 MW

Storage capacity in MWh: not published by SSEN.

Each site is grouped by its first energy source, as the register names it.

How busy is each primary substation?

Each primary substation at this grid supply point in the November 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Primary substationBulk supply pointSitesConnectedAccepted to connect
Not stated1362 MW191 MW
Not stated117 MW–
Not stated1–<0.1 MW
Not stated47 MW179 MW

Search and filter all 19 sites at FIDDES

Listed at under 1 MW in SSEN’s November 2026 edition

1 site last listed here at 1 MW or over is listed in this edition at under 1 MW. QueueWatch keeps its page for six months.

What changed recently

Changes to sites here found in both editions of each pair, newest first.

October 2026 edition to November 2026 edition: 18 sites matched. 2 sites at this grid supply point couldn’t be matched between the two editions, because their details changed or they appear in only one.

2 sites without a match in the other edition
In the November 2026 edition only (1)
In the October 2026 edition only (1)
  • SALES SCOTLAND ENERGETICSNorth of Scotland (SHEPD)Accepted to connectListed at under 1 MW in the November 2026 edition0.225 MW
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

How power reaches a site

A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.