Distribution / SSEN / Grid supply point

AXMINSTER

Grid supply point in Southern England (SEPD)

SSEN Embedded Capacity Register, November 2026 edition

25sites of 1 MW and over
408 MWcapacity
126 MWconnected (15 sites)
282 MWaccepted to connect (10 sites)

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Solar20280 MW107 MW173 MW
Storage258.7 MW–58.7 MW
Other or not stated254 MW4 MW50 MW
Gas and other fossil115.2 MW15.2 MW–

Storage capacity in MWh: not published by SSEN.

Each site is grouped by its first energy source, as the register names it.

How busy is each primary substation?

Each primary substation at this grid supply point in the November 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Primary substationBulk supply pointSitesConnectedAccepted to connect
YEOVIL335 MW15.2 MW
YEOVIL38.7 MW8.4 MW
YEOVIL115.2 MW–
YEOVIL111.4 MW–
YEOVIL111.4 MW–
YEOVIL17.6 MW–
YEOVIL15.3 MW–
YEOVIL15 MW–
YEOVIL14.3 MW–
YEOVIL14.1 MW–
YEOVIL14 MW–
YEOVIL13.9 MW–
YEOVIL11.3 MW–
YEOVIL59 MW138 MW
Not stated3–120 MW

Search and filter all 25 sites at AXMINSTER

Not found among the sites of 1 MW and over in SSEN’s November 2026 edition

1 site last found at this grid supply point was not found among this edition’s sites of 1 MW and over by its MPAN, grid reference or name and postcode. QueueWatch keeps its page for six months and does not say whether it has left the register.

What changed recently

Changes to sites here found in both editions of each pair, newest first.

October 2026 edition to November 2026 edition: 25 sites matched. Every October site and every November site at this grid supply point had a match in the other edition.

  • BINDWELL LANE - PVNovember 2025 editionTarget energisation date moved from 6 Dec 2024 to 7 Oct 2026 (22 months later)
  • CONRAD (YEOVIL) LIMITEDApril 2025 editionTechnology stated as Gas and other fossil (not stated in the March 2025 edition)
  • BINDWELL LANE - PVJanuary 2025 editionTarget energisation date stated as 6 Dec 2024 (not stated in the November 2024 edition)
  • BINDWELL LANE - PVJune 2024 editionCapacity changed from 9 MW to 11.7 MW
  • BOWDEN LANE SOLAR PARK LIMITEDNovember 2023 editionCapacity changed from 4.13 MW to 3.924 MW
  • SUTTON BRIDGE PVNovember 2023 editionCapacity stated as 5.273 MW (not stated in the October 2023 edition)
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

How power reaches a site

A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.