QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.

Pyewipe Farm PV

Pyewipe Farm PV at Keadby

Northern Powergrid Embedded Capacity Register 1MW and Over, October 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
Not published by Northern Powergrid
Status
Accepted to connect
Customer
Pyewipe Farm PV
Site name
Pyewipe Farm PV
Address
Pyewipe Farm, Redbourne Road, Gainsborough, Lincolnshire, DN21 4TG
Grid reference
Easting 497757, northing 398299
Licence area
Yorkshire (Northern Powergrid)
Grid supply point
Keadby
Bulk supply point
Santon
Primary substation
Hibaldstow
Connection voltage
11 kV
Technology group
Solar
Energy source 1
Solar, Photovoltaic: 1 MW registered
Registered capacity
1 MW
Change to maximum export capacity
1 MW
Change to maximum import capacity
0 MW
Flexible connection
No
In a connection queue
Not published by Northern Powergrid
Date accepted
28 Aug 2026
Date connected
Not stated
Distribution reinforcement reference
Not published by Northern Powergrid
Transmission reinforcement reference
Not published by Northern Powergrid
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
14 Oct 2026
Tracked since
October 2026 edition

Change history

Tracked since the October 2026 edition.

Changes to the details QueueWatch tracks, newest first.

No changes to show: it has been found in one edition.

Also at Keadby

GSP view

66 other sites at this grid supply point in the October 2026 edition. In all, the sites here total 2.4 GW: 0.6 GW connected, 1.8 GW accepted to connect.

See all 66

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose