Bradford West
Grid supply point in Yorkshire (Northern Powergrid)
Northern Powergrid Embedded Capacity Register 1MW and Over, November 2026 edition
Capacity by technology
| Technology | Sites | Capacity | Connected | Accepted to connect |
|---|---|---|---|---|
| Storage | 8 | 779 MW | 87 MW | 692 MW |
| Solar | 3 | 75 MW | – | 75 MW |
| Wind | 2 | 36.6 MW | 18.6 MW | 18 MW |
| Gas and other fossil | 9 | 35.8 MW | 35.8 MW | – |
| Bioenergy and waste | 2 | 19.1 MW | 1.1 MW | 18 MW |
| Other or not stated | 1 | 1.2 MW | 1.2 MW | – |
Storage capacity in MWh: no site here states any.
Each site is grouped by its first energy source, as the register names it.
How busy is each primary substation?
Each primary substation at this grid supply point in the November 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.
Site, company and substation names are shown as they appear in the registers, including capitalisation.
| Primary substation | Bulk supply point | Sites | Connected | Accepted to connect | |||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Bradford West A BESS | 1 | – | 200 MW | ||||||||||||||||
1 site, 200 MW: 200 MW accepted to connect
| |||||||||||||||||||
| Peat Dyke Farm BESS | 1 | – | 100 MW | ||||||||||||||||
1 site, 100 MW: 100 MW accepted to connect
| |||||||||||||||||||
| Allerton Road BESS | 1 | – | 99.9 MW | ||||||||||||||||
1 site, 99.9 MW: 99.9 MW accepted to connect
| |||||||||||||||||||
| Old Allen Road BESS | 1 | – | 99.9 MW | ||||||||||||||||
1 site, 99.9 MW: 99.9 MW accepted to connect
| |||||||||||||||||||
| Lane Side BESS | 1 | – | 99.8 MW | ||||||||||||||||
1 site, 99.8 MW: 99.8 MW accepted to connect
| |||||||||||||||||||
| Harop Lane BESS | 1 | 87 MW | – | ||||||||||||||||
1 site, 87 MW: 87 MW connected
| |||||||||||||||||||
| Menston | 1 | – | 45 MW | ||||||||||||||||
1 site, 45 MW: 45 MW accepted to connect
| |||||||||||||||||||
| Menston | 1 | – | 27.9 MW | ||||||||||||||||
1 site, 27.9 MW: 27.9 MW accepted to connect
| |||||||||||||||||||
| Menston | 1 | 4.6 MW | – | ||||||||||||||||
1 site, 4.6 MW: 4.6 MW connected
| |||||||||||||||||||
| Menston | 2 | 3.3 MW | – | ||||||||||||||||
2 sites, 3.3 MW: 3.3 MW connected
| |||||||||||||||||||
| Midland Road BESS | 1 | – | 80 MW | ||||||||||||||||
1 site, 80 MW: 80 MW accepted to connect
| |||||||||||||||||||
| Silsden | 1 | – | 18 MW | ||||||||||||||||
1 site, 18 MW: 18 MW accepted to connect
| |||||||||||||||||||
| Silsden | 1 | – | 18 MW | ||||||||||||||||
1 site, 18 MW: 18 MW accepted to connect
| |||||||||||||||||||
| Silsden | 1 | 6.4 MW | – | ||||||||||||||||
1 site, 6.4 MW: 6.4 MW connected
| |||||||||||||||||||
| Silsden | 1 | – | 2.1 MW | ||||||||||||||||
1 site, 2.1 MW: 2.1 MW accepted to connect
| |||||||||||||||||||
| Silsden | 1 | 1.1 MW | – | ||||||||||||||||
1 site, 1.1 MW: 1.1 MW connected
| |||||||||||||||||||
| Girlington | 2 | 11.9 MW | 12 MW | ||||||||||||||||
2 sites, 23.9 MW: 11.9 MW connected, 12 MW accepted to connect
| |||||||||||||||||||
| Girlington | 2 | 6.7 MW | – | ||||||||||||||||
2 sites, 6.7 MW: 6.7 MW connected
| |||||||||||||||||||
| Girlington | 1 | 1.4 MW | – | ||||||||||||||||
1 site, 1.4 MW: 1.4 MW connected
| |||||||||||||||||||
| Holmfield | 1 | 18.6 MW | – | ||||||||||||||||
1 site, 18.6 MW: 18.6 MW connected
| |||||||||||||||||||
| Bradford | 2 | 2.7 MW | – | ||||||||||||||||
2 sites, 2.7 MW: 2.7 MW connected
| |||||||||||||||||||
Not found among the sites of 1 MW and over in Northern Powergrid’s November 2026 edition
1 site last found at this grid supply point was not found among this edition’s sites of 1 MW and over by its MPAN, grid reference or name and postcode. QueueWatch keeps its page for six months and does not say whether it has left the register.
- Girlington BESS last found in the July 2026 edition
What changed recently
Changes to sites here found in both editions of each pair, newest first.
October 2026 edition to November 2026 edition: 25 sites matched. Every October site and every November site at this grid supply point had a match in the other edition.
- Bradford Royal InfirmaryAugust 2026 editionCapacity changed from 5.094 MW to 5.214 MW
- Bradford Royal InfirmaryAugust 2026 editionExport capacity changed from 0 MW to 0.778 MW
- Otley Road CHPMay 2026 editionExport capacity changed from 1.25 MW to 3.308 MW
- Otley Road CHPMay 2026 editionStatus changed from “accepted to connect” to “connected”
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?
How power reaches a site
A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.