Allerton Road BESS
Allerton Road BESS at Bradford West
Northern Powergrid Embedded Capacity Register 1MW and Over, November 2026 edition
Site, company and substation names are shown as they appear in the registers, including capitalisation.
- Target energisation date
- Not published by Northern Powergrid
- Status
- Accepted to connect
- Customer
- Allerton Road BESS
- Site name
- Allerton Road BESS
- Address
- Allerton Road, Allerton, Bradford, West Yorkshire, BD15 8AB
- Grid reference
- Easting 410283, northing 434503
- Licence area
- Yorkshire (Northern Powergrid)
- Grid supply point
- Bradford West
- Bulk supply point
- Allerton Road BESS
- Primary substation
- Allerton Road BESS Direct
- Connection voltage
- 132 kV
- Technology group
- Storage
- Energy source 1
- Stored Energy (all stored energy irrespective of the original energy source), Storage - Electrochemical (Batteries): 99.9 MW registered
- Registered capacity
- 99.9 MW
- Change to maximum export capacity
- 99.9 MW
- Change to maximum import capacity
- 99.902 MW
- Flexible connection
- Yes
- In a connection queue
- Not published by Northern Powergrid
- Date accepted
- 13 Nov 2024
- Date connected
- Not stated
- Distribution reinforcement reference
- Not published by Northern Powergrid
- Transmission reinforcement reference
- Not published by Northern Powergrid
- Export MPAN
- Not stated
- Import MPAN
- Not stated
- Last updated
- 9 Dec 2024
- Tracked since
- March 2026 edition
What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?
Change history
Tracked since the March 2026 edition, across 9 editions.
Changes to the details QueueWatch tracks, newest first.
No change to any detail QueueWatch tracks.
Also at Bradford West
GSP view24 other sites at this grid supply point in the November 2026 edition. In all, the sites here total 946 MW: 144 MW connected, 802 MW accepted to connect.
- Bradford West A BESSBradford West A BESS, Storage, Bradford West A BESS Direct primaryAccepted200 MW
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose