ASHTON OLD ROAD GENERATION (ASHTON STOR)
STOR 128 LTD at STALYBRIDGE GSP
ENWL Embedded Capacity Register 2 – 1MW and above, September 2026 edition
Site, company and substation names are shown as they appear in the registers, including capitalisation.
- Date connected
- 2 Dec 2024
- Status
- Connected
- Customer
- STOR 128 LTD
- Site name
- ASHTON OLD ROAD GENERATION (ASHTON STOR)
- Address
- ASHTON OLD ROAD, ASHTON OLD ROAD, MANCHESTER, MANCHESTER, OL7 0PJ
- Grid reference
- Easting 392623, northing 397618
- Licence area
- North West England (ENWL)
- Grid supply point
- STALYBRIDGE GSP
- Bulk supply point
- DROYLSDEN
- Primary substation
- Not stated
- Connection voltage
- 33 kV
- Technology group
- Gas and other fossil
- Energy source 1
- FOSSIL - OIL, ENGINE (COMBUSTION / RECIPROCATING): 20 MW registered
- Registered capacity
- 21.053 MW
- Maximum export capacity
- 20 MW
- Maximum import capacity
- 0 MW
- Change to maximum import capacity
- 0 MW
- Flexible connection
- No
- In a connection queue
- Not stated
- Date accepted
- Not stated
- Target energisation date
- Not stated
- Distribution reinforcement reference
- Not published by ENWL
- Transmission reinforcement reference
- Not stated
- Export MPAN
- Not stated
- Import MPAN
- Not stated
- Last updated
- 14 Jan 2025
- Tracked since
- May 2026 edition
Change history
Tracked since the May 2026 edition, across 2 editions.
Changes to its status, capacity, technology or customer, newest first.
No change to its status, capacity, technology or customer.
Also at STALYBRIDGE GSP
GSP view28 other sites at this grid supply point in the September 2026 edition. In all, the sites here total 366 MW: 174 MW connected, 192 MW accepted to connect.
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose