Distribution / ENWL / Grid supply point

STALYBRIDGE GSP

Grid supply point in North West England (ENWL)

ENWL Embedded Capacity Register 2 – 1MW and above, October 2026 edition

The register spells this grid supply point more than one way: “STALYBRIDGE GSP” (25 sites) and “STALYBRIDGE” (4 sites).

29sites of 1 MW and over
366 MWcapacity
174 MWconnected (15 sites)
192 MWaccepted to connect (14 sites)

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Storage10187 MW72 MW115 MW
Gas and other fossil16173 MW98 MW75 MW
Solar24.4 MW3 MW1.4 MW
Bioenergy and waste11 MW1 MW–

Storage capacity in MWh: not published by ENWL.

Each site is grouped by its first energy source, as the register names it.

How busy is each primary substation?

Each primary substation at this grid supply point in the October 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Primary substationBulk supply pointSitesConnectedAccepted to connect
BUXTON960 MW102 MW
HYDE212.1 MW–
HYDE29.1 MW–
HYDE16 MW–
HYDE262 MW–
NEW MILLS21 MW9 MW
NEW MILLS1–31.6 MW
HARTSHEAD-HEYROD2–7.1 MW
HARTSHEAD-HEYROD11.2 MW–
HARTSHEAD-HEYROD1–21.1 MW
DROYLSDEN1–1.5 MW
DROYLSDEN121.1 MW–
STUART ST1–10 MW
STUART ST1–5.3 MW
STUART ST1–4 MW
STUART ST11.5 MW–

Search and filter all 29 sites at STALYBRIDGE GSP

What changed recently

Changes to sites here found in both editions of each pair, newest first.

September 2026 edition to October 2026 edition: 29 sites matched. Every September site and every October site at this grid supply point had a match in the other edition.

No change to any detail QueueWatch tracks for these sites so far.

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

How power reaches a site

A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.