HUNTERSTON GRID 1 LTD
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Hunterston Battery Storage Facility | Hunterston East 400kV substation | Storage | 200 | 10 Mar 2028 +24 mo | Gate 2 | Consents Approved |
| Hunterston Energy Storage Facility | Ayrshire Grid 400kV Substation | Storage | 200 | 17 Mar 2028 +31 mo | Gate 2 | Consents Approved |
Recent changes
- Hunterston Battery Storage FacilitySouth Scotland, StorageStatus changed from Scoping to Consents Approved
- Hunterston Energy Storage FacilitySouth Scotland, StorageStatus changed from Scoping to Consents Approved
- Hunterston Energy Storage FacilitySouth Scotland, StorageCustomer changed from HUNTERSTON GRID 2 LTD to HUNTERSTON GRID 1 LTD
- Hunterston Battery Storage FacilitySouth Scotland, StorageTechnology changed from Demand, Storage to Storage, Reactive compensation
- Hunterston Battery Storage FacilitySouth Scotland, StorageConnection point changed from Ayrshire Grid 400kV Substation to Hunterston East 400kV substation
- Hunterston Battery Storage FacilitySouth Scotland, StorageConnection date moved from 9 Mar 2026 to 10 Mar 2028 (+24 months)+24 mo
- Hunterston Battery Storage FacilitySouth Scotland, StorageGiven a Gate 2 connection offerGate 2
- Hunterston Energy Storage FacilitySouth Scotland, StorageConnection date moved from 27 Aug 2025 to 17 Mar 2028 (+31 months)+31 mo
- Hunterston Energy Storage FacilitySouth Scotland, StorageGiven a Gate 2 connection offerGate 2
- Hunterston Battery Storage FacilitySouth Scotland, StorageCustomer changed from FLEXIBLEGRIDPOWER2 LTD to HUNTERSTON GRID 1 LTD
- Hunterston Energy Storage FacilitySouth Scotland, StorageCustomer changed from ENERGYGRIDPOWER2 LTD to HUNTERSTON GRID 2 LTD
- Hunterston Battery Storage FacilitySouth Scotland, StorageConnection date moved from 20 Aug 2025 to 9 Mar 2026 (+7 months)+7 mo
- Hunterston Battery Storage FacilitySouth Scotland, StorageTechnology changed from Storage, Reactive compensation to Demand, Storage
- Hunterston Battery Storage FacilitySouth Scotland, StorageConnection date moved from 12 Apr 2024 to 20 Aug 2025 (+16 months)+16 mo
- Hunterston Energy Storage FacilitySouth Scotland, StorageConnection date moved from 12 Apr 2024 to 27 Aug 2025 (+16 months)+16 mo
- Hunterston Battery Storage FacilitySouth Scotland, StorageConnection date moved from 16 Apr 2024 to 12 Apr 2024 (4 days earlier)
- Hunterston Energy Storage FacilitySouth Scotland, StorageConnection date moved from 16 Apr 2024 to 12 Apr 2024 (4 days earlier)
- Hunterston Battery Storage FacilitySouth Scotland, StorageConnection date moved from 16 Dec 2024 to 16 Apr 2024 (−8 months)−8 mo
- Hunterston Energy Storage FacilitySouth Scotland, StorageConnection date moved from 16 Dec 2024 to 16 Apr 2024 (−8 months)−8 mo
- Hunterston Battery Storage FacilitySouth Scotland, StorageConnection date moved from 12 Apr 2024 to 16 Dec 2024 (+8 months)+8 mo
- Hunterston Energy Storage FacilitySouth Scotland, StorageConnection date moved from 12 Apr 2024 to 16 Dec 2024 (+8 months)+8 mo
- Hunterston Battery Storage FacilitySouth Scotland, StorageSubstation name updated in the register (from Ayrshire Grid 400 kV Substation to Ayrshire Grid 400kV Substation)
- Hunterston Energy Storage FacilitySouth Scotland, StorageSubstation name updated in the register (from Ayrshire Grid 400 kV Substation to Ayrshire Grid 400kV Substation)
- Hunterston Battery Storage FacilitySouth Scotland, StorageTechnology changed from Storage to Storage, Reactive compensation
- Hunterston Energy Storage FacilitySouth Scotland, StorageAdded to the registerNew
- Hunterston Battery Storage FacilitySouth Scotland, StorageConnection point changed from Hunterston 400kV Substation to Ayrshire Grid 400 kV Substation
- Hunterston Battery Storage FacilitySouth Scotland, StorageTechnology changed from Storage, Reactive compensation to Storage
- Hunterston Battery Storage FacilitySouth Scotland, StorageConnection date moved from 4 Dec 2024 to 12 Apr 2024 (−8 months)−8 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose