Hunterston Battery Storage Facility
- Connection date
- 10 Mar 2028 +24 months since 9 Dec
- Gate
- Gate 2
- Status
- Consents Approved
- Technology
- Storage + Reactive compensation
- Total capacity
- 200 MW
- Connected now
- 0 MW
- Still to connect
- 200 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-001155
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 18 Sep 2026 registerStatus changed from Scoping to Consents Approved
- 16 Jun 2026 registerTechnology changed from Demand, Storage to Storage, Reactive compensation
- 5 Jun 2026 registerConnection point changed from Ayrshire Grid 400kV Substation to Hunterston East 400kV substation
- 5 Jun 2026 registerConnection date moved from 9 Mar 2026 to 10 Mar 2028 (+24 months)
- 5 Jun 2026 registerGiven a Gate 2 connection offer
- 12 May 2026 registerCustomer changed from FLEXIBLEGRIDPOWER2 LTD to HUNTERSTON GRID 1 LTD
- 21 Nov 2025 registerConnection date moved from 20 Aug 2025 to 9 Mar 2026 (+7 months)
- 29 Jul 2025 registerTechnology changed from Storage, Reactive compensation to Demand, Storage
- 29 Apr 2025 registerConnection date moved from 12 Apr 2024 to 20 Aug 2025 (+16 months)
- 31 May 2024 registerConnection date moved from 16 Apr 2024 to 12 Apr 2024 (4 days earlier)
- 26 Apr 2024 registerConnection date moved from 16 Dec 2024 to 16 Apr 2024 (−8 months)
- 27 Feb 2024 registerConnection date moved from 12 Apr 2024 to 16 Dec 2024 (+8 months)
- 23 Dec 2022 registerSubstation name updated in the register (from Ayrshire Grid 400 kV Substation to Ayrshire Grid 400kV Substation)
- 30 Nov 2021 registerTechnology changed from Storage to Storage, Reactive compensation
- 28 Sep 2021 registerConnection point changed from Hunterston 400kV Substation to Ayrshire Grid 400 kV Substation
- 30 Apr 2021 registerTechnology changed from Storage, Reactive compensation to Storage
- 26 Feb 2021 registerConnection date moved from 4 Dec 2024 to 12 Apr 2024 (−8 months)
Also at Hunterston East 400kV
Substation view1 other project, 400 MW still to connect at this substation in total. 200 MW is due to connect here before this project’s connection date of 10 Mar 2028.