Hunterston Energy Storage Facility
- Connection date
- 17 Mar 2028 +31 months since 9 Dec
- Gate
- Gate 2
- Status
- Consents Approved
- Technology
- Storage
- Total capacity
- 200 MW
- Connected now
- 0 MW
- Still to connect
- 200 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-001644
- In the register since
- October 2021
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 18 Sep 2026 registerStatus changed from Scoping to Consents Approved
- 19 Jun 2026 registerCustomer changed from HUNTERSTON GRID 2 LTD to HUNTERSTON GRID 1 LTD
- 5 Jun 2026 registerConnection date moved from 27 Aug 2025 to 17 Mar 2028 (+31 months)
- 5 Jun 2026 registerGiven a Gate 2 connection offer
- 20 Mar 2026 registerCustomer changed from ENERGYGRIDPOWER2 LTD to HUNTERSTON GRID 2 LTD
- 29 Apr 2025 registerConnection date moved from 12 Apr 2024 to 27 Aug 2025 (+16 months)
- 31 May 2024 registerConnection date moved from 16 Apr 2024 to 12 Apr 2024 (4 days earlier)
- 26 Apr 2024 registerConnection date moved from 16 Dec 2024 to 16 Apr 2024 (−8 months)
- 27 Feb 2024 registerConnection date moved from 12 Apr 2024 to 16 Dec 2024 (+8 months)
- 23 Dec 2022 registerSubstation name updated in the register (from Ayrshire Grid 400 kV Substation to Ayrshire Grid 400kV Substation)
- 29 Oct 2021 registerAdded to the register
Also at Ayrshire Grid 400kV Substation
Substation viewNo other projects in the register at this connection point.