Hunterston East 400kV
South Scotland, SP Energy Networks
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Highview Hunterston East Cryobattery | HVS SITECO LTD | Storage | 200 | 31 Oct 2027 | Not stated | Consents Approved |
| Hunterston Battery Storage Facility | HUNTERSTON GRID 1 LTD | Storage | 200 | 10 Mar 2028 +24 mo | Gate 2 | Consents Approved |
Left the register since January 2021: Hunterston Synchronous Compensation (0 MW), Tinz Hunterston Sync Comp (1 MW).
Recent changes
- Hunterston Battery Storage FacilitySouth Scotland, StorageStatus changed from Scoping to Consents Approved
- Hunterston Battery Storage FacilitySouth Scotland, StorageTechnology changed from Demand, Storage to Storage, Reactive compensation
- Hunterston Battery Storage FacilitySouth Scotland, StorageConnection point changed from Ayrshire Grid 400kV Substation to Hunterston East 400kV substation
- Hunterston Battery Storage FacilitySouth Scotland, StorageConnection date moved from 9 Mar 2026 to 10 Mar 2028 (+24 months)+24 mo
- Hunterston Battery Storage FacilitySouth Scotland, StorageGiven a Gate 2 connection offerGate 2
- Hunterston Battery Storage FacilitySouth Scotland, StorageCustomer changed from FLEXIBLEGRIDPOWER2 LTD to HUNTERSTON GRID 1 LTD
- Hunterston Battery Storage FacilitySouth Scotland, StorageConnection date moved from 20 Aug 2025 to 9 Mar 2026 (+7 months)+7 mo
- Hunterston Battery Storage FacilitySouth Scotland, StorageTechnology changed from Storage, Reactive compensation to Demand, Storage
- Highview Hunterston East CryobatterySouth Scotland, StorageCustomer changed from HVS SITEGO LTD to HVS SITECO LTD
- Hunterston Battery Storage FacilitySouth Scotland, StorageConnection date moved from 12 Apr 2024 to 20 Aug 2025 (+16 months)+16 mo
- Highview Hunterston East CryobatterySouth Scotland, StorageCustomer changed from HVS GRIDCO LTD to HVS SITEGO LTD
- Highview Hunterston East CryobatterySouth Scotland, StorageStatus changed from Scoping to Consents Approved
- Highview Hunterston East CryobatterySouth Scotland, StorageSubstation name updated in the register (from Hunterston East 400kV Substation to Hunterston East 400kV)
- Highview Hunterston East CryobatterySouth Scotland, StorageCapacity changed from 99.8 MW to 200 MW
- Highview Hunterston East CryobatterySouth Scotland, StorageConnection date moved from 30 Jun 2024 to 31 Oct 2027 (+40 months)+40 mo
- Highview Hunterston East CryobatterySouth Scotland, StorageTechnology changed from Storage, Reactive compensation to Demand, Storage, Reactive compensation
- Hunterston Battery Storage FacilitySouth Scotland, StorageConnection date moved from 16 Apr 2024 to 12 Apr 2024 (4 days earlier)
- Hunterston Battery Storage FacilitySouth Scotland, StorageConnection date moved from 16 Dec 2024 to 16 Apr 2024 (−8 months)−8 mo
- Hunterston Battery Storage FacilitySouth Scotland, StorageConnection date moved from 12 Apr 2024 to 16 Dec 2024 (+8 months)+8 mo
- Highview Hunterston East CryobatterySouth Scotland, StorageConnection point changed from Highview Hunterston East Cryobattery 400kV Substation to Hunterston East 400kV Substation
- Hunterston Battery Storage FacilitySouth Scotland, StorageSubstation name updated in the register (from Ayrshire Grid 400 kV Substation to Ayrshire Grid 400kV Substation)
- Tinz Hunterston Sync CompSouth Scotland, OtherLeft the register (1 MW from 30 May 2025)1 MW
- Hunterston Synchronous CompensationSouth Scotland, OtherLeft the register (0 MW from 30 Oct 2024)0 MW
- Highview Hunterston East CryobatterySouth Scotland, StorageTechnology changed from Storage to Storage, Reactive compensation
- Hunterston Battery Storage FacilitySouth Scotland, StorageTechnology changed from Storage to Storage, Reactive compensation
- Hunterston Synchronous CompensationSouth Scotland, OtherAdded to the registerNew
- Tinz Hunterston Sync CompSouth Scotland, OtherAdded to the registerNew
- Hunterston Battery Storage FacilitySouth Scotland, StorageConnection point changed from Hunterston 400kV Substation to Ayrshire Grid 400 kV Substation
- Highview Hunterston East CryobatterySouth Scotland, StorageConnection date moved from 30 Oct 2024 to 30 Jun 2024 (−4 months)−4 mo
- Highview Hunterston East CryobatterySouth Scotland, StorageTechnology changed from Storage, Reactive compensation to Storage
- Hunterston Battery Storage FacilitySouth Scotland, StorageTechnology changed from Storage, Reactive compensation to Storage
- Hunterston Battery Storage FacilitySouth Scotland, StorageConnection date moved from 4 Dec 2024 to 12 Apr 2024 (−8 months)−8 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose