Ayrshire Grid 400kV Substation
South Scotland, SP Energy Networks
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Hunterston Energy Storage Facility | HUNTERSTON GRID 1 LTD | Storage | 200 | 17 Mar 2028 +31 mo | Gate 2 | Consents Approved |
Recent changes
- Hunterston Energy Storage FacilitySouth Scotland, StorageStatus changed from Scoping to Consents Approved
- Hunterston Energy Storage FacilitySouth Scotland, StorageCustomer changed from HUNTERSTON GRID 2 LTD to HUNTERSTON GRID 1 LTD
- Hunterston Energy Storage FacilitySouth Scotland, StorageConnection date moved from 27 Aug 2025 to 17 Mar 2028 (+31 months)+31 mo
- Hunterston Energy Storage FacilitySouth Scotland, StorageGiven a Gate 2 connection offerGate 2
- Hunterston Energy Storage FacilitySouth Scotland, StorageCustomer changed from ENERGYGRIDPOWER2 LTD to HUNTERSTON GRID 2 LTD
- Hunterston Energy Storage FacilitySouth Scotland, StorageConnection date moved from 12 Apr 2024 to 27 Aug 2025 (+16 months)+16 mo
- Hunterston Energy Storage FacilitySouth Scotland, StorageConnection date moved from 16 Apr 2024 to 12 Apr 2024 (4 days earlier)
- Hunterston Energy Storage FacilitySouth Scotland, StorageConnection date moved from 16 Dec 2024 to 16 Apr 2024 (−8 months)−8 mo
- Hunterston Energy Storage FacilitySouth Scotland, StorageConnection date moved from 12 Apr 2024 to 16 Dec 2024 (+8 months)+8 mo
- Hunterston Energy Storage FacilitySouth Scotland, StorageSubstation name updated in the register (from Ayrshire Grid 400 kV Substation to Ayrshire Grid 400kV Substation)
- Hunterston Energy Storage FacilitySouth Scotland, StorageAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?