- Connection date
- 31 Oct 2030
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Solar + Onshore wind
- Total capacity
- 400 MW
- Connected now
- 0 MW
- Still to connect
- 400 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002087
- In the register since
- June 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 16 Jan 2026 registerCustomer changed from ENSO GREEN HOLDINGS LIMITED to ENSO GREEN HOLDINGS Q LIMITED
- 9 Dec 2025 registerMarked as Gate 1
- 30 Jun 2023 registerAdded to the register
Also at Rassau 400kV Substation
Substation view1 other project, 400 MW still to connect at this substation in total.