Capenhurst Tertiary
ENSO GREEN HOLDINGS Q LIMITED at Capenhurst 400kV Substation
- Connection date
- 31 Oct 2027 −24 months since 9 Dec
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 57 MW
- Connected now
- 0 MW
- Still to connect
- 57 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002162
- In the register since
- June 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 10 Oct 2026 registerConnection date moved from 30 Oct 2029 to 31 Oct 2027 (−24 months)
- 1 May 2026 registerMarked as Gate 1
- 27 Jun 2025 registerRestructured from 2 stages (49.9 MW from 31 Oct 2025, 7.1 MW from 31 Oct 2027) to 1 stage (57 MW from 30 Oct 2029). First connection date +48 months
- 29 Apr 2025 registerCustomer changed from ENSO GREEN HOLDINGS Q LIMITED to ENSO GREEN HOLDINGS LIMITED
- 28 Feb 2025 registerCustomer changed from ENSO GREEN HOLDINGS LIMITED to ENSO GREEN HOLDINGS Q LIMITED
- 26 Nov 2024 registerAdded to the register
- 31 May 2024 registerLeft the register (400 MW from 31 Oct 2030)
- 30 Jun 2023 registerAdded to the register
Also at Capenhurst 400kV Substation
Substation viewNo other projects in the register at this connection point.