West Burton 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| West Burton B | WEST BURTON B LIMITED | Thermal (gas, biomass, waste) | 548 | 30 Oct 2027 | Not stated | Built |
| West Burton Solar Project | WEST BURTON SOLAR PROJECT LIMITED | Storage with solar or wind | 480 | 31 Oct 2028 −1 mo | Gate 2 | Consents Approved |
| Steeple Solar Farm | Steeple Solar Farm Limited | Storage with solar or wind | 600 | 31 Oct 2029 | Not stated | Scoping |
Left the register since January 2021: West Burton A (0 MW), West Burton Energy Storage (0 MW).
Recent changes
- West Burton Solar ProjectEngland and Wales, Storage with solar or windConnection date moved from 30 Nov 2028 to 31 Oct 2028 (−1 month)−1 mo
- West Burton Solar ProjectEngland and Wales, Storage with solar or windStatus changed from Scoping to Consents Approved
- West Burton Solar ProjectEngland and Wales, Storage with solar or windGiven a Gate 2 connection offerGate 2
- Steeple Solar FarmEngland and Wales, Storage with solar or windCustomer changed from Renewable Energy Systems Limited to Steeple Solar Farm Limited
- Steeple Solar FarmEngland and Wales, Storage with solar or windRenamed from Midlands Estate Energy Park
- West Burton BEngland and Wales, Thermal (gas, biomass, waste)Stage removed (0 MW from 30 Oct 2033)
- West Burton BEngland and Wales, Thermal (gas, biomass, waste)New stage added (0 MW from 30 Oct 2033)
- Steeple Solar FarmEngland and Wales, Storage with solar or windTechnology changed from Storage, Solar, Onshore wind to Storage, Solar
- West Burton BEngland and Wales, Thermal (gas, biomass, waste)Restructured from 1 stage (1,333 MW connected + 500 MW from 31 Oct 2032) to 2 stages (1,333 MW connected + 500 MW from 30 Oct 2027, 48 MW from 30 Oct 2034). First connection date −60 months−60 mo
- West Burton BEngland and Wales, Thermal (gas, biomass, waste)Status changed from Scoping to Built
- West Burton BEngland and Wales, Thermal (gas, biomass, waste)Capacity changed from 0 MW to 500 MW
- West Burton BEngland and Wales, Thermal (gas, biomass, waste)Connection date set to 31 Oct 2032
- West Burton BEngland and Wales, Thermal (gas, biomass, waste)Status changed from Built to Scoping
- West Burton AEngland and Wales, Thermal (gas, biomass, waste)Left the register (900 MW connected − 900 MW from 1 Apr 2023)0 MW
- West Burton Solar ProjectEngland and Wales, Storage with solar or windRenamed from Laughton Solar Park
- West Burton Solar ProjectEngland and Wales, Storage with solar or windCustomer changed from LAUGHTON SOLAR PARK LIMITED to West Burton Solar Project Limited
- Steeple Solar FarmEngland and Wales, Storage with solar or windSubstation name updated in the register (from West Burton 400kV to West Burton 400kV Substation)
- West Burton BEngland and Wales, Thermal (gas, biomass, waste)Substation name updated in the register (from West Burton 400kV to West Burton 400kV Substation)
- West Burton Solar ProjectEngland and Wales, Storage with solar or windRenamed from West Burton Solar Park
- West Burton Solar ProjectEngland and Wales, Storage with solar or windCustomer changed from West Burton Solar Project Limited to LAUGHTON SOLAR PARK LIMITED
- West Burton Solar ProjectEngland and Wales, Storage with solar or windSubstation name updated in the register (from West Burton 400kV to West Burton 400kV Substation)
- West Burton AEngland and Wales, Thermal (gas, biomass, waste)Substation name updated in the register (from West Burton 400kV to West Burton 400kV Substation)
- West Burton Solar ProjectEngland and Wales, Storage with solar or windRenamed from Laughton Solar Park
- West Burton Solar ProjectEngland and Wales, Storage with solar or windCustomer changed from LAUGHTON SOLAR PARK LIMITED to West Burton Solar Project Limited
- West Burton BEngland and Wales, Thermal (gas, biomass, waste)Customer changed from EDF ENERGY (THERMAL GENERATION) LIMITED to WEST BURTON B LIMITED
- West Burton BEngland and Wales, Thermal (gas, biomass, waste)Technology changed from Gas (CCGT) to Gas (CCGT), Storage
- Steeple Solar FarmEngland and Wales, Storage with solar or windAdded to the registerNew
- West Burton AEngland and Wales, Thermal (gas, biomass, waste)1,075 MW no longer connected
- West Burton AEngland and Wales, Thermal (gas, biomass, waste)Capacity changed from −1,075 MW to −900 MW
- West Burton AEngland and Wales, Thermal (gas, biomass, waste)Connection date moved from 1 Apr 2022 to 1 Apr 2023
- West Burton AEngland and Wales, Thermal (gas, biomass, waste)Capacity changed from 0 MW to −1,075 MW
- West Burton AEngland and Wales, Thermal (gas, biomass, waste)Connection date set to 1 Apr 2022
- West Burton Energy StorageEngland and Wales, StorageLeft the register (0 MW)0 MW
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose