Steeple Solar Farm
- Connection date
- 31 Oct 2029
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 600 MW
- Connected now
- 0 MW
- Still to connect
- 600 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001945
- In the register since
- May 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 22 May 2026 registerCustomer changed from Renewable Energy Systems Limited to Steeple Solar Farm Limited
- 21 Apr 2026 registerRenamed from Midlands Estate Energy Park
- 27 Jun 2025 registerTechnology changed from Storage, Solar, Onshore wind to Storage, Solar
- 23 Dec 2022 registerSubstation name updated in the register (from West Burton 400kV to West Burton 400kV Substation)
- 31 May 2022 registerAdded to the register
Also at West Burton 400kV Substation
Substation view2 other projects, 1.6 GW still to connect at this substation in total. 980 MW is due to connect here before this project’s connection date of 31 Oct 2029.