Warley 275kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Warley | WARLEY BATTERY STORAGE LIMITED | Storage | 57 | 30 Oct 2028 +14 mo | Gate 2 | Consents Approved |
| Warley Battery Energy Storage | LONDON AND ESSEX ENERGY LIMITED | Storage | 200 | 31 Oct 2029 | Gate 1 | Scoping |
| Lebanon Farm 2 BESS | CEDARTECH ENERGY LTD | Storage | 275 | 31 Oct 2030 | Not stated | Scoping |
| Warley PV & BESS | O&G Solar (SPV 36) Limited | Storage | 250 | 31 Oct 2031 | Not stated | Scoping |
| Codham Hall BESS | PULSE CLEAN ENERGY LIMITED | Storage | 249 | 31 Oct 2037 | Gate 1 | Scoping |
| Blanket’s Farm | Noventum Power Solar 9 Limited | Storage | 200 | 31 Oct 2038 | Gate 1 | Scoping |
| Warley (tertiary) | WARLEY GREEN LIMITED | Storage with solar or wind | 0 | Connected | Not stated | Built |
Left the register since January 2021: Warley 2 (200 MW).
Recent changes
- WarleyEngland and Wales, StorageGiven a Gate 2 connection offerGate 2
- Warley Battery Energy StorageEngland and Wales, StorageConnection date moved from 31 Aug 2027 to 31 Oct 2029 (+26 months)+26 mo
- Warley Battery Energy StorageEngland and Wales, StorageConnection date moved from 31 Oct 2029 to 31 Aug 2027 (−26 months)−26 mo
- WarleyEngland and Wales, StorageConnection date moved from 31 Aug 2027 to 30 Oct 2028 (+14 months)+14 mo
- Warley (tertiary)England and Wales, Storage with solar or windRestructured from 2 stages (49.9 MW from 31 Jul 2023, 7.1 MW from 28 Jun 2024) to 1 stage (57 MW connected)
- Warley Battery Energy StorageEngland and Wales, StorageMarked as Gate 1
- Warley Battery Energy StorageEngland and Wales, StorageCustomer changed from ABBEY PROPERTIES CAMBRIDGESHIRE LIMITED to LONDON AND ESSEX ENERGY LIMITED
- Blanket’s FarmEngland and Wales, StorageMarked as Gate 1
- Codham Hall BESSEngland and Wales, StorageConnection point changed from Warley 400kV Substation to Warley 275kV Substation
- Codham Hall BESSEngland and Wales, StorageMarked as Gate 1
- Lebanon Farm 2 BESSEngland and Wales, StorageCustomer changed from Bluestone Energy Ltd to CEDARTECH ENERGY LTD
- WarleyEngland and Wales, StorageCustomer changed from WARLEY BATTERY STORAGE to WARLEY BATTERY STORAGE LIMITED
- Warley 2England and Wales, StorageLeft the register (150 MW from 31 Oct 2029, 50 MW from 31 Oct 2033)200 MW
- Warley PV & BESSEngland and Wales, StorageTechnology changed from Storage, Solar to Storage
- WarleyEngland and Wales, StorageConnection date moved from 30 Jun 2024 to 31 Aug 2027 (+38 months)+38 mo
- Blanket’s FarmEngland and Wales, StorageAdded to the registerNew
- Codham Hall BESSEngland and Wales, StorageConnection point changed from Warley 275kV Substation to Warley 400kV Substation
- Codham Hall BESSEngland and Wales, StorageConnection date moved from 31 Oct 2030 to 31 Oct 2037 (+84 months)+84 mo
- Lebanon Farm 2 BESSEngland and Wales, StorageAdded to the registerNew
- Codham Hall BESSEngland and Wales, StorageAdded to the registerNew
- WarleyEngland and Wales, StorageConnection point changed from Warley 400kV Substation to Warley 275kV Substation
- Warley PV & BESSEngland and Wales, StorageConnection point changed from Warley GSP to Warley 275kV Substation
- Warley PV & BESSEngland and Wales, StorageAdded to the registerNew
- Warley 2England and Wales, StorageNew stage added (50 MW from 31 Oct 2033)
- WarleyEngland and Wales, StorageCustomer changed from CSE19 LIMITED to WARLEY BATTERY STORAGE
- Warley Battery Energy StorageEngland and Wales, StorageAdded to the registerNew
- WarleyEngland and Wales, StorageCapacity changed from 49.5 MW to 57 MW
- WarleyEngland and Wales, StorageConnection date moved from 1 Jul 2023 to 30 Jun 2024 (+12 months)+12 mo
- WarleyEngland and Wales, StorageStatus changed from Scoping to Consents Approved
- Warley 2England and Wales, StorageConnection point changed from Warley GSP to Warley 275kV Substation
- WarleyEngland and Wales, StorageSubstation name updated in the register (from Warley 400kV to Warley 400kV Substation)
- Warley (tertiary)England and Wales, Storage with solar or windSubstation name updated in the register (from Warley 275kV to Warley 275kV Substation)
- Warley 2England and Wales, StorageSubstation name updated in the register (from Warley to Warley GSP)
- Warley (tertiary)England and Wales, Storage with solar or windCustomer changed from ENSO GREEN HOLDINGS LIMITED to Warley Green Limited
- Warley 2England and Wales, StorageAdded to the registerNew
- Warley (tertiary)England and Wales, Storage with solar or windStage 1: Connection date moved from 31 Oct 2022 to 31 Jul 2023 (+9 months)+9 mo
- Warley (tertiary)England and Wales, Storage with solar or windStage 2: Connection date moved from 31 Oct 2023 to 28 Jun 2024 (+8 months)+8 mo
- WarleyEngland and Wales, StorageTechnology changed from Gas (CCGT) to Storage
- WarleyEngland and Wales, StorageCustomer changed from CLEARSTONE SERVICES LIMITED to CSE19 Limited
- WarleyEngland and Wales, StorageConnection date moved from 7 Jan 2023 to 1 Jul 2023 (+6 months)+6 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose