PULSE CLEAN ENERGY LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Greenock Road BESS | Greenock Road 275kV Substation | Storage | 250 | 31 Oct 2033 | Gate 1 | Scoping |
| Hunterston PARC BESS | Hunterston 400/132kV | Storage | 250 | 31 Oct 2033 | Not stated | Scoping |
| Codham Hall BESS | Warley 275kV Substation | Storage | 249 | 31 Oct 2037 | Gate 1 | Scoping |
| Elland BESS | Leeds North Connection Node E 275kV Substation | Storage | 249 | 31 Oct 2037 | Gate 1 | Scoping |
Left the register since January 2021: Conexus North BESS Facility (200 MW).
Recent changes
- Elland BESSEngland and Wales, StorageConnection point changed from Leeds North Connection Node E to Leeds North Connection Node E 275kV Substation
- Elland BESSEngland and Wales, StorageMarked as Gate 1
- Greenock Road BESSSouth Scotland, StorageMarked as Gate 1
- Codham Hall BESSEngland and Wales, StorageConnection point changed from Warley 400kV Substation to Warley 275kV Substation
- Codham Hall BESSEngland and Wales, StorageMarked as Gate 1
- Conexus North BESS FacilitySouth Scotland, StorageLeft the register (200 MW from 31 Oct 2031)200 MW
- Hunterston PARC BESSSouth Scotland, StorageConnection point changed from Hunterston 400kV Substation to Hunterston 400/132kV
- Codham Hall BESSEngland and Wales, StorageConnection point changed from Warley 275kV Substation to Warley 400kV Substation
- Greenock Road BESSSouth Scotland, StorageAdded to the registerNew
- Elland BESSEngland and Wales, StorageConnection point changed from Elland 275kV Substation to Leeds North Connection Node E
- Codham Hall BESSEngland and Wales, StorageConnection date moved from 31 Oct 2030 to 31 Oct 2037 (+84 months)+84 mo
- Hunterston PARC BESSSouth Scotland, StorageAdded to the registerNew
- Codham Hall BESSEngland and Wales, StorageAdded to the registerNew
- Elland BESSEngland and Wales, StorageAdded to the registerNew
- Conexus North BESS FacilitySouth Scotland, StorageAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose