WARLEY BATTERY STORAGE LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Warley | Warley 275kV Substation | Storage | 57 | 30 Oct 2028 +14 mo | Gate 2 | Consents Approved |
Recent changes
- WarleyEngland and Wales, StorageGiven a Gate 2 connection offerGate 2
- WarleyEngland and Wales, StorageConnection date moved from 31 Aug 2027 to 30 Oct 2028 (+14 months)+14 mo
- WarleyEngland and Wales, StorageCustomer changed from WARLEY BATTERY STORAGE to WARLEY BATTERY STORAGE LIMITED
- WarleyEngland and Wales, StorageConnection date moved from 30 Jun 2024 to 31 Aug 2027 (+38 months)+38 mo
- WarleyEngland and Wales, StorageConnection point changed from Warley 400kV Substation to Warley 275kV Substation
- WarleyEngland and Wales, StorageCustomer changed from CSE19 LIMITED to WARLEY BATTERY STORAGE
- WarleyEngland and Wales, StorageCapacity changed from 49.5 MW to 57 MW
- WarleyEngland and Wales, StorageConnection date moved from 1 Jul 2023 to 30 Jun 2024 (+12 months)+12 mo
- WarleyEngland and Wales, StorageStatus changed from Scoping to Consents Approved
- WarleyEngland and Wales, StorageSubstation name updated in the register (from Warley 400kV to Warley 400kV Substation)
- WarleyEngland and Wales, StorageTechnology changed from Gas (CCGT) to Storage
- WarleyEngland and Wales, StorageCustomer changed from CLEARSTONE SERVICES LIMITED to CSE19 Limited
- WarleyEngland and Wales, StorageConnection date moved from 7 Jan 2023 to 1 Jul 2023 (+6 months)+6 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?