Trent Valley South Connection Node A 400kV
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| CODDINGTON BESS | SHAW-ENERGI LTD | Storage | 300 | 30 Oct 2034 | Gate 1 | Scoping |
| Leadenham High Impact Green Energy Hub | TELIS ENERGY UK LIMITED | Multi-technology hub | 1,000 | 30 Oct 2034 | Gate 1 | Scoping |
| Vicarage Drove BESS | UK Transition Power Holdings Limited | Storage | 1,200 | 30 Oct 2034 | Gate 1 | Scoping |
Recent changes
- CODDINGTON BESSEngland and Wales, StorageConnection date moved from 31 Oct 2034 to 30 Oct 2034 (1 day earlier)
- Leadenham High Impact Green Energy HubEngland and Wales, Multi-technology hubConnection date moved from 31 Oct 2034 to 30 Oct 2034 (1 day earlier)
- Vicarage Drove BESSEngland and Wales, StorageMarked as Gate 1
- Vicarage Drove BESSEngland and Wales, StorageConnection point changed from Trent Valley South Connection Node A 400k to Trent Valley South Connection Node A 400kV
- CODDINGTON BESSEngland and Wales, StorageConnection point changed from Coddington 400kV Substation to Trent Valley South Connection Node A 400kV
- CODDINGTON BESSEngland and Wales, StorageMarked as Gate 1
- Leadenham High Impact Green Energy HubEngland and Wales, Multi-technology hubConnection point changed from Trent Valley South Connection Node A 400k to Trent Valley South Connection Node A 400kV
- Leadenham High Impact Green Energy HubEngland and Wales, Multi-technology hubMarked as Gate 1
- Vicarage Drove BESSEngland and Wales, Storage1,200 MW no longer connected
- Vicarage Drove BESSEngland and Wales, StorageAdded to the registerNew
- Leadenham High Impact Green Energy HubEngland and Wales, Multi-technology hubConnection point changed from Navenby 400kV Substation to Trent Valley South Connection Node A 400k
- Leadenham High Impact Green Energy HubEngland and Wales, Multi-technology hubStatus changed from Awaiting Consents to Scoping
- CODDINGTON BESSEngland and Wales, StorageAdded to the registerNew
- Leadenham High Impact Green Energy HubEngland and Wales, Multi-technology hubAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose