QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

SHAW-ENERGI LTD

Customer named in the TEC register

3projects in the register
900 MWstill to connect
0 MWof that with Gate 2 offers
0 MWconnected now

Projects

ProjectConnection siteTechnologyQueued MWConnection dateGateStatus
Waltham Cross BESSLondon North East Connection Node A 400kVStorage30031 Oct 2033Gate 1Scoping
CODDINGTON BESSTrent Valley South Connection Node A 400kVStorage30030 Oct 2034Gate 1Scoping
DRAGON GREEN BESSSussex and Romney Connection Node B 400kV SubstationStorage30031 Oct 2037Gate 1Scoping

Left the register since January 2021: Lister Drive (57 MW), Carnegie Road Tertiary (57 MW).

Recent changes

  • CODDINGTON BESSEngland and Wales, StorageConnection date moved from 31 Oct 2034 to 30 Oct 2034 (1 day earlier)
  • CODDINGTON BESSEngland and Wales, StorageConnection point changed from Coddington 400kV Substation to Trent Valley South Connection Node A 400kV
  • CODDINGTON BESSEngland and Wales, StorageMarked as Gate 1
  • DRAGON GREEN BESSEngland and Wales, StorageConnection point changed from Bolney 400kV Substation to Sussex and Romney Connection Node B 400kV Substation
  • DRAGON GREEN BESSEngland and Wales, StorageMarked as Gate 1
  • Waltham Cross BESSEngland and Wales, StorageConnection point changed from Waltham Cross 400kV Substation to London North East Connection Node A 400kV
  • Waltham Cross BESSEngland and Wales, StorageMarked as Gate 1
  • CODDINGTON BESSEngland and Wales, StorageAdded to the registerNew
  • DRAGON GREEN BESSEngland and Wales, StorageAdded to the registerNew
  • Waltham Cross BESSEngland and Wales, StorageAdded to the registerNew
  • Lister DriveEngland and Wales, StorageLeft the register (57 MW from 30 Jun 2023)57 MW
  • Carnegie Road TertiaryEngland and Wales, StorageLeft the register (57 MW from 30 Jun 2023)57 MW
  • Lister DriveEngland and Wales, StorageCapacity changed from 50 MW to 57 MW
  • Carnegie Road TertiaryEngland and Wales, StorageAdded to the registerNew
  • Lister DriveEngland and Wales, StorageConnection date moved from 1 May 2023 to 30 Jun 2023 (+2 months)+2 mo
  • Lister DriveEngland and Wales, StorageConnection date moved from 5 Jan 2023 to 1 May 2023 (+4 months)+4 mo
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO