SHAW-ENERGI LTD
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Waltham Cross BESS | London North East Connection Node A 400kV | Storage | 300 | 31 Oct 2033 | Gate 1 | Scoping |
| CODDINGTON BESS | Trent Valley South Connection Node A 400kV | Storage | 300 | 30 Oct 2034 | Gate 1 | Scoping |
| DRAGON GREEN BESS | Sussex and Romney Connection Node B 400kV Substation | Storage | 300 | 31 Oct 2037 | Gate 1 | Scoping |
Left the register since January 2021: Lister Drive (57 MW), Carnegie Road Tertiary (57 MW).
Recent changes
- CODDINGTON BESSEngland and Wales, StorageConnection date moved from 31 Oct 2034 to 30 Oct 2034 (1 day earlier)
- CODDINGTON BESSEngland and Wales, StorageConnection point changed from Coddington 400kV Substation to Trent Valley South Connection Node A 400kV
- CODDINGTON BESSEngland and Wales, StorageMarked as Gate 1
- DRAGON GREEN BESSEngland and Wales, StorageConnection point changed from Bolney 400kV Substation to Sussex and Romney Connection Node B 400kV Substation
- DRAGON GREEN BESSEngland and Wales, StorageMarked as Gate 1
- Waltham Cross BESSEngland and Wales, StorageConnection point changed from Waltham Cross 400kV Substation to London North East Connection Node A 400kV
- Waltham Cross BESSEngland and Wales, StorageMarked as Gate 1
- CODDINGTON BESSEngland and Wales, StorageAdded to the registerNew
- DRAGON GREEN BESSEngland and Wales, StorageAdded to the registerNew
- Waltham Cross BESSEngland and Wales, StorageAdded to the registerNew
- Lister DriveEngland and Wales, StorageLeft the register (57 MW from 30 Jun 2023)57 MW
- Carnegie Road TertiaryEngland and Wales, StorageLeft the register (57 MW from 30 Jun 2023)57 MW
- Lister DriveEngland and Wales, StorageCapacity changed from 50 MW to 57 MW
- Carnegie Road TertiaryEngland and Wales, StorageAdded to the registerNew
- Lister DriveEngland and Wales, StorageConnection date moved from 1 May 2023 to 30 Jun 2023 (+2 months)+2 mo
- Lister DriveEngland and Wales, StorageConnection date moved from 5 Jan 2023 to 1 May 2023 (+4 months)+4 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?