CODDINGTON BESS
SHAW-ENERGI LTD at Trent Valley South Connection Node A 400kV
- Connection date
- 30 Oct 2034
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 300 MW
- Connected now
- 0 MW
- Still to connect
- 300 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-003666
- In the register since
- January 2024
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 10 Oct 2026 registerConnection date moved from 31 Oct 2034 to 30 Oct 2034 (1 day earlier)
- 7 Apr 2026 registerConnection point changed from Coddington 400kV Substation to Trent Valley South Connection Node A 400kV
- 7 Apr 2026 registerMarked as Gate 1
- 30 Jan 2024 registerAdded to the register
Also at Trent Valley South Connection Node A 400kV
Substation view2 other projects, 2.5 GW still to connect at this substation in total.