Spennymoor PV & BESS
- Connection date
- 30 Jul 2032
- Gate
- Not stated
- Status
- Scoping
- Technology
- Demand + Storage + Solar
- Total capacity
- 49.9 MW
- Connected now
- 0 MW
- Still to connect
- 49.9 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002035
- In the register since
- July 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Jul 2025 registerRenamed from Spennymoor BESS
- 29 Jul 2025 registerConnection date moved from 30 Jun 2032 to 30 Jul 2032 (+1 month)
- 29 Jul 2025 registerTechnology changed from Storage, Solar to Demand, Storage, Solar
- 27 Jun 2025 registerTechnology changed from Storage to Storage, Solar
- 28 Feb 2025 registerCapacity changed from 50 MW to 49.9 MW
- 28 Feb 2025 registerConnection date moved from 30 Jul 2032 to 30 Jun 2032 (−1 month)
- 28 Jul 2023 registerAdded to the register
Also at Spennymoor 400kV Substation
Substation view3 other projects, 850 MW still to connect at this substation in total. 49.9 MW is due to connect here before this project’s connection date of 30 Jul 2032.